Banc One's Halcyon Days of Merger Integration Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Banc One's Halcyon Days of Merger Integration case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Banc One's Halcyon Days of Merger Integration case study is a Harvard Business School (HBR) case study written by L.J. Bourgeois. The Banc One's Halcyon Days of Merger Integration (referred as “Banc Banks” from here on) case study provides evaluation & decision scenario in field of Communication. It also touches upon business topics such as - Value proposition, Growth strategy, Joint ventures, Mergers & acquisitions.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Banc One's Halcyon Days of Merger Integration Case Study


The year 1992 had been most successful for Banc One placing it first among the 25 largest banks in the United States. It had achieved this stellar record through a strategy of nuts-and-bolts banking that included focusing on serving retail and middle-market customers through community banks, investing in technologies that created competitive advantages, and treating bank acquisitions as an ongoing line of business. The newly appointed chairman of Diversified Services at Banc One is responsible for products in the nonbanking areas of securities, insurance, leasing, consumer finance, asset management, and mortgage. But the growth of Diversified Services has fueled apprehension that the fundamental values on which the bank's success had been built were changing. In this context, the chairman is charged with persuading the presidents of the affiliate banks to adopt his nontraditional banking products into their local banks to enlist them in a strategic partnership with Diversified Services.


Case Authors : L.J. Bourgeois

Topic : Communication

Related Areas : Growth strategy, Joint ventures, Mergers & acquisitions




Calculating Net Present Value (NPV) at 6% for Banc One's Halcyon Days of Merger Integration Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10014835) -10014835 - -
Year 1 3457592 -6557243 3457592 0.9434 3261879
Year 2 3982942 -2574301 7440534 0.89 3544804
Year 3 3957450 1383149 11397984 0.8396 3322751
Year 4 3229805 4612954 14627789 0.7921 2558308
TOTAL 14627789 12687743




The Net Present Value at 6% discount rate is 2672908

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Profitability Index
3. Net Present Value
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Banc Banks have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Banc Banks shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Banc One's Halcyon Days of Merger Integration

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Communication Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Banc Banks often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Banc Banks needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10014835) -10014835 - -
Year 1 3457592 -6557243 3457592 0.8696 3006602
Year 2 3982942 -2574301 7440534 0.7561 3011676
Year 3 3957450 1383149 11397984 0.6575 2602088
Year 4 3229805 4612954 14627789 0.5718 1846651
TOTAL 10467017


The Net NPV after 4 years is 452182

(10467017 - 10014835 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10014835) -10014835 - -
Year 1 3457592 -6557243 3457592 0.8333 2881327
Year 2 3982942 -2574301 7440534 0.6944 2765932
Year 3 3957450 1383149 11397984 0.5787 2290191
Year 4 3229805 4612954 14627789 0.4823 1557583
TOTAL 9495033


The Net NPV after 4 years is -519802

At 20% discount rate the NPV is negative (9495033 - 10014835 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Banc Banks to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Banc Banks has a NPV value higher than Zero then finance managers at Banc Banks can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Banc Banks, then the stock price of the Banc Banks should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Banc Banks should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Banc One's Halcyon Days of Merger Integration

References & Further Readings

L.J. Bourgeois (2018), "Banc One's Halcyon Days of Merger Integration Harvard Business Review Case Study. Published by HBR Publications.


Samji Electronics SWOT Analysis / TOWS Matrix

Technology , Communications Equipment


Tecnoglass SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Harvest SWOT Analysis / TOWS Matrix

Technology , Software & Programming


LHN SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Imd Companies SWOT Analysis / TOWS Matrix

Healthcare , Healthcare Facilities


Espec Corp SWOT Analysis / TOWS Matrix

Technology , Scientific & Technical Instr.


Fluor SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


EXFO Inc SWOT Analysis / TOWS Matrix

Technology , Communications Equipment