Paramount Distributing Inc.: The Popcorn Predicament Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Paramount Distributing Inc.: The Popcorn Predicament case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Paramount Distributing Inc.: The Popcorn Predicament case study is a Harvard Business School (HBR) case study written by Michael Taylor. The Paramount Distributing Inc.: The Popcorn Predicament (referred as “Buying Behaviour” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, .

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Paramount Distributing Inc.: The Popcorn Predicament Case Study


This B2B role play case and the six role play supplements describe an account manager's seven month sales process and the customer's buying process that led to a lost order. It is an excellent case to explore organizational buying behaviour, the discipline of the selling process and the management of sales resources (time) as an asset. It can be included in an introductory marketing course at the MBA or undergraduate level. It is equally effective for executive development. It also fits in a B2B marketing course to explore organizational buying behaviour, or in the introduction module in a sales management course.


Case Authors : Michael Taylor

Topic : Leadership & Managing People

Related Areas :




Calculating Net Present Value (NPV) at 6% for Paramount Distributing Inc.: The Popcorn Predicament Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10029688) -10029688 - -
Year 1 3469504 -6560184 3469504 0.9434 3273117
Year 2 3969732 -2590452 7439236 0.89 3533047
Year 3 3936561 1346109 11375797 0.8396 3305213
Year 4 3237042 4583151 14612839 0.7921 2564040
TOTAL 14612839 12675417




The Net Present Value at 6% discount rate is 2645729

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Internal Rate of Return
3. Payback Period
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Buying Behaviour shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Buying Behaviour have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Paramount Distributing Inc.: The Popcorn Predicament

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Buying Behaviour often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Buying Behaviour needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10029688) -10029688 - -
Year 1 3469504 -6560184 3469504 0.8696 3016960
Year 2 3969732 -2590452 7439236 0.7561 3001688
Year 3 3936561 1346109 11375797 0.6575 2588353
Year 4 3237042 4583151 14612839 0.5718 1850789
TOTAL 10457790


The Net NPV after 4 years is 428102

(10457790 - 10029688 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10029688) -10029688 - -
Year 1 3469504 -6560184 3469504 0.8333 2891253
Year 2 3969732 -2590452 7439236 0.6944 2756758
Year 3 3936561 1346109 11375797 0.5787 2278102
Year 4 3237042 4583151 14612839 0.4823 1561073
TOTAL 9487188


The Net NPV after 4 years is -542500

At 20% discount rate the NPV is negative (9487188 - 10029688 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Buying Behaviour to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Buying Behaviour has a NPV value higher than Zero then finance managers at Buying Behaviour can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Buying Behaviour, then the stock price of the Buying Behaviour should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Buying Behaviour should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Paramount Distributing Inc.: The Popcorn Predicament

References & Further Readings

Michael Taylor (2018), "Paramount Distributing Inc.: The Popcorn Predicament Harvard Business Review Case Study. Published by HBR Publications.


Patrimoine Et Comm SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Trada Maritime SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


Top Global Ltd SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Shenzhen Expressway SWOT Analysis / TOWS Matrix

Transportation , Misc. Transportation


Brimag -L SWOT Analysis / TOWS Matrix

Consumer Cyclical , Appliance & Tool


Plains All American Pipeline SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


Gosuncn A SWOT Analysis / TOWS Matrix

Technology , Communications Equipment


Westone Info Ind A SWOT Analysis / TOWS Matrix

Services , Security Systems & Services


Sajohaepyo SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Zhongzai Resources SWOT Analysis / TOWS Matrix

Services , Waste Management Services