Schweiz Aluminum Alloy Division Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Schweiz Aluminum Alloy Division case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Schweiz Aluminum Alloy Division case study is a Harvard Business School (HBR) case study written by Benson P. Shapiro. The Schweiz Aluminum Alloy Division (referred as “Alloy Aluminum” from here on) case study provides evaluation & decision scenario in field of Management. It also touches upon business topics such as - Value proposition, Ethics, Pricing, Product development.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Schweiz Aluminum Alloy Division Case Study


In January, 2008, Schweiz Aluminum Alloy Division is preparing to introduce its new GH 1000 alloy. The Division was a worldwide leader in the marketing of high strength, relatively exotic aluminum alloys. Recently, one of its talented metallurgists had developed a new formulation for one alloy in the 7000 series of high strength, hard alloys. The formulation was significantly lower in cost than the previous one used, but had absolutely no impact on the performance characteristics and appearance. For all practical purposes, it was identical to the existing more expensive alloy that it would replace. Andrew McAndrews, product manager for high strength aluminum alloys, was responsible for setting a price for the new alloy.


Case Authors : Benson P. Shapiro

Topic : Management

Related Areas : Ethics, Pricing, Product development




Calculating Net Present Value (NPV) at 6% for Schweiz Aluminum Alloy Division Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10000322) -10000322 - -
Year 1 3448060 -6552262 3448060 0.9434 3252887
Year 2 3959821 -2592441 7407881 0.89 3524227
Year 3 3937021 1344580 11344902 0.8396 3305599
Year 4 3244895 4589475 14589797 0.7921 2570261
TOTAL 14589797 12652973




The Net Present Value at 6% discount rate is 2652651

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Profitability Index
3. Net Present Value
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Alloy Aluminum shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Alloy Aluminum have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Schweiz Aluminum Alloy Division

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Management Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Alloy Aluminum often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Alloy Aluminum needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10000322) -10000322 - -
Year 1 3448060 -6552262 3448060 0.8696 2998313
Year 2 3959821 -2592441 7407881 0.7561 2994194
Year 3 3937021 1344580 11344902 0.6575 2588655
Year 4 3244895 4589475 14589797 0.5718 1855279
TOTAL 10436441


The Net NPV after 4 years is 436119

(10436441 - 10000322 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10000322) -10000322 - -
Year 1 3448060 -6552262 3448060 0.8333 2873383
Year 2 3959821 -2592441 7407881 0.6944 2749876
Year 3 3937021 1344580 11344902 0.5787 2278369
Year 4 3244895 4589475 14589797 0.4823 1564861
TOTAL 9466488


The Net NPV after 4 years is -533834

At 20% discount rate the NPV is negative (9466488 - 10000322 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Alloy Aluminum to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Alloy Aluminum has a NPV value higher than Zero then finance managers at Alloy Aluminum can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Alloy Aluminum, then the stock price of the Alloy Aluminum should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Alloy Aluminum should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Schweiz Aluminum Alloy Division

References & Further Readings

Benson P. Shapiro (2018), "Schweiz Aluminum Alloy Division Harvard Business Review Case Study. Published by HBR Publications.


Tokai Carbon SWOT Analysis / TOWS Matrix

Basic Materials , Chemical Manufacturing


artec technologies SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Actoz Soft SWOT Analysis / TOWS Matrix

Technology , Computer Services


Pacific Radiance Ltd SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


Hinto Energy Inc SWOT Analysis / TOWS Matrix

Energy , Oil & Gas - Integrated


Food Empire Holdings Ltd SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Elixir Petroleum SWOT Analysis / TOWS Matrix

Energy , Oil & Gas - Integrated


Augmentum Fintech SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services