Johnson Beverage, Inc. Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Johnson Beverage, Inc. case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Johnson Beverage, Inc. case study is a Harvard Business School (HBR) case study written by Luann J. Lynch. The Johnson Beverage, Inc. (referred as “Johnson Beverage” from here on) case study provides evaluation & decision scenario in field of Organizational Development. It also touches upon business topics such as - Value proposition, Sales.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Johnson Beverage, Inc. Case Study


Jack Johnson, owner of Johnson Beverage, has just received notice that one of his largest and most loyal customers may want to negotiate a lower price for its product purchases. Information compiled by Johnson's accountant, where customer service costs are allocated to customers as a percentage of revenue, suggests that profit margin on the customer is too low to withstand a price decrease. Students are asked to design an activity-based system for allocating customer service costs and to use it to estimate customer profitability for several customers. The revised costs reflect that the customer places low demands on customer service resources and is sufficiently profitable to permit Johnson Beverage to negotiate on price to preserve the business. Additional analysis identifies some unprofitable customers, previously thought to be profitable, that offer opportunities for strategic decisions that lead to profit improvement.


Case Authors : Luann J. Lynch

Topic : Organizational Development

Related Areas : Sales




Calculating Net Present Value (NPV) at 6% for Johnson Beverage, Inc. Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10028920) -10028920 - -
Year 1 3453061 -6575859 3453061 0.9434 3257605
Year 2 3955715 -2620144 7408776 0.89 3520572
Year 3 3960435 1340291 11369211 0.8396 3325258
Year 4 3247781 4588072 14616992 0.7921 2572547
TOTAL 14616992 12675981




The Net Present Value at 6% discount rate is 2647061

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Payback Period
3. Internal Rate of Return
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Johnson Beverage have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Johnson Beverage shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Johnson Beverage, Inc.

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Organizational Development Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Johnson Beverage often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Johnson Beverage needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10028920) -10028920 - -
Year 1 3453061 -6575859 3453061 0.8696 3002662
Year 2 3955715 -2620144 7408776 0.7561 2991089
Year 3 3960435 1340291 11369211 0.6575 2604050
Year 4 3247781 4588072 14616992 0.5718 1856929
TOTAL 10454730


The Net NPV after 4 years is 425810

(10454730 - 10028920 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10028920) -10028920 - -
Year 1 3453061 -6575859 3453061 0.8333 2877551
Year 2 3955715 -2620144 7408776 0.6944 2747024
Year 3 3960435 1340291 11369211 0.5787 2291918
Year 4 3247781 4588072 14616992 0.4823 1566252
TOTAL 9482746


The Net NPV after 4 years is -546174

At 20% discount rate the NPV is negative (9482746 - 10028920 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Johnson Beverage to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Johnson Beverage has a NPV value higher than Zero then finance managers at Johnson Beverage can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Johnson Beverage, then the stock price of the Johnson Beverage should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Johnson Beverage should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What can impact the cash flow of the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Johnson Beverage, Inc.

References & Further Readings

Luann J. Lynch (2018), "Johnson Beverage, Inc. Harvard Business Review Case Study. Published by HBR Publications.


Hoegh LNG Partners LP SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


Aeon Fantasy Co Ltd SWOT Analysis / TOWS Matrix

Services , Recreational Activities


America Movil ADR SWOT Analysis / TOWS Matrix

Services , Communications Services


Hubei Golden Ring SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber


Keppel REIT SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


CBS A SWOT Analysis / TOWS Matrix

Services , Broadcasting & Cable TV


Korvest Ltd SWOT Analysis / TOWS Matrix

Basic Materials , Misc. Fabricated Products


Profire Ene SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Continental Gold SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver