Borealis Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Borealis case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Borealis case study is a Harvard Business School (HBR) case study written by Robert S. Kaplan, Bjorn N. Jorgensen. The Borealis (referred as “Borealis Process” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Budgeting, Costs, Forecasting.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Borealis Case Study


When Borealis, a European producer of plastics, used a traditional, time-consuming budgeting process, the budget was quickly out of date in a competitive environment characterized by continually changing input and output prices and dynamic market conditions. This case describes the process that led Borealis to replace its budgets with four targeted management tools: rolling financial forecasts, Balanced Scorecard, activity based costing, and investment management. It also discusses the process of implementing the new measurement and control systems.


Case Authors : Robert S. Kaplan, Bjorn N. Jorgensen

Topic : Finance & Accounting

Related Areas : Budgeting, Costs, Forecasting




Calculating Net Present Value (NPV) at 6% for Borealis Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10017055) -10017055 - -
Year 1 3464712 -6552343 3464712 0.9434 3268596
Year 2 3972562 -2579781 7437274 0.89 3535566
Year 3 3939044 1359263 11376318 0.8396 3307297
Year 4 3222914 4582177 14599232 0.7921 2552850
TOTAL 14599232 12664309




The Net Present Value at 6% discount rate is 2647254

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Internal Rate of Return
3. Net Present Value
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Borealis Process have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Borealis Process shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Borealis

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Borealis Process often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Borealis Process needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10017055) -10017055 - -
Year 1 3464712 -6552343 3464712 0.8696 3012793
Year 2 3972562 -2579781 7437274 0.7561 3003828
Year 3 3939044 1359263 11376318 0.6575 2589985
Year 4 3222914 4582177 14599232 0.5718 1842712
TOTAL 10449318


The Net NPV after 4 years is 432263

(10449318 - 10017055 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10017055) -10017055 - -
Year 1 3464712 -6552343 3464712 0.8333 2887260
Year 2 3972562 -2579781 7437274 0.6944 2758724
Year 3 3939044 1359263 11376318 0.5787 2279539
Year 4 3222914 4582177 14599232 0.4823 1554260
TOTAL 9479783


The Net NPV after 4 years is -537272

At 20% discount rate the NPV is negative (9479783 - 10017055 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Borealis Process to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Borealis Process has a NPV value higher than Zero then finance managers at Borealis Process can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Borealis Process, then the stock price of the Borealis Process should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Borealis Process should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Borealis

References & Further Readings

Robert S. Kaplan, Bjorn N. Jorgensen (2018), "Borealis Harvard Business Review Case Study. Published by HBR Publications.


Sinosoft Technology SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Panasonic SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Parts


Brunswick SWOT Analysis / TOWS Matrix

Consumer Cyclical , Recreational Products


Jacquet Metal SWOT Analysis / TOWS Matrix

Basic Materials , Misc. Fabricated Products


Blackrock World Mining SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Nippon REIT SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Kinder Morgan SWOT Analysis / TOWS Matrix

Utilities , Natural Gas Utilities


Denyo Co Ltd SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


SunOpta Inc. SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Crops


DDS SWOT Analysis / TOWS Matrix

Technology , Computer Peripherals