Biltwell Shears, Inc. Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Biltwell Shears, Inc. case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Biltwell Shears, Inc. case study is a Harvard Business School (HBR) case study written by Thomas R. Piper. The Biltwell Shears, Inc. (referred as “Shears Biltwell” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Financial analysis, Financial management, Manufacturing.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Biltwell Shears, Inc. Case Study


A senior loan officer is reviewing the recent performance of a company that has failed to repay its loan as scheduled. The failure results from a cyclical downturn in sales, coupled with a lag in cutting back production. Inventory risk is minimal. This case is an updated version of Cutrite Shears.


Case Authors : Thomas R. Piper

Topic : Finance & Accounting

Related Areas : Financial analysis, Financial management, Manufacturing




Calculating Net Present Value (NPV) at 6% for Biltwell Shears, Inc. Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10008653) -10008653 - -
Year 1 3458857 -6549796 3458857 0.9434 3263073
Year 2 3960739 -2589057 7419596 0.89 3525044
Year 3 3964325 1375268 11383921 0.8396 3328524
Year 4 3231133 4606401 14615054 0.7921 2559360
TOTAL 14615054 12676000




The Net Present Value at 6% discount rate is 2667347

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Payback Period
3. Net Present Value
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Shears Biltwell shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Shears Biltwell have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Biltwell Shears, Inc.

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Shears Biltwell often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Shears Biltwell needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10008653) -10008653 - -
Year 1 3458857 -6549796 3458857 0.8696 3007702
Year 2 3960739 -2589057 7419596 0.7561 2994888
Year 3 3964325 1375268 11383921 0.6575 2606608
Year 4 3231133 4606401 14615054 0.5718 1847411
TOTAL 10456608


The Net NPV after 4 years is 447955

(10456608 - 10008653 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10008653) -10008653 - -
Year 1 3458857 -6549796 3458857 0.8333 2882381
Year 2 3960739 -2589057 7419596 0.6944 2750513
Year 3 3964325 1375268 11383921 0.5787 2294170
Year 4 3231133 4606401 14615054 0.4823 1558224
TOTAL 9485287


The Net NPV after 4 years is -523366

At 20% discount rate the NPV is negative (9485287 - 10008653 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Shears Biltwell to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Shears Biltwell has a NPV value higher than Zero then finance managers at Shears Biltwell can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Shears Biltwell, then the stock price of the Shears Biltwell should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Shears Biltwell should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Biltwell Shears, Inc.

References & Further Readings

Thomas R. Piper (2018), "Biltwell Shears, Inc. Harvard Business Review Case Study. Published by HBR Publications.


Excel Co Ltd SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


TCS Group Holding PLC SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services


Lianluo Smart SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Ipmuda SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Scout24 AG SWOT Analysis / TOWS Matrix

Technology , Computer Services


Foseco India Ltd SWOT Analysis / TOWS Matrix

Basic Materials , Chemical Manufacturing


Ihq SWOT Analysis / TOWS Matrix

Services , Recreational Activities


Blonder Tongue Labs SWOT Analysis / TOWS Matrix

Technology , Communications Equipment


Softpower Intl SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures