NPV solution for Gilead Sciences, Inc.: Access Program case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Gilead Sciences, Inc.: Access Program case study is a Harvard Business School (HBR) case study written by V. Kasturi Rangan, Katharine Lee. The Gilead Sciences, Inc.: Access Program (referred as “Sciences Color.gilead” from here on) case study provides evaluation & decision scenario in field of Sales & Marketing. It also touches upon business topics such as - Value proposition, Emerging markets, Intellectual property, Marketing, Product development, Sales.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Gilead Sciences, Inc.: Access Program Case Study


To maximize their effectiveness, color cases should be printed in color.Gilead Sciences, the U.S. leader in HIV/AIDS medicines, with global sales of $5.4 billion in 2009, had undertaken several innovative actions to make its anti-viral products available to over 100 low- and middle-income countries. Having reached nearly 680,000 patients by the middle of 2009, the company's senior managers contemplated how to reach 2 million patients by 2012.


Case Authors : V. Kasturi Rangan, Katharine Lee

Topic : Sales & Marketing

Related Areas : Emerging markets, Intellectual property, Marketing, Product development, Sales




Calculating Net Present Value (NPV) at 6% for Gilead Sciences, Inc.: Access Program Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10004898) -10004898 - -
Year 1 3469315 -6535583 3469315 0.9434 3272939
Year 2 3978017 -2557566 7447332 0.89 3540421
Year 3 3942981 1385415 11390313 0.8396 3310603
Year 4 3250277 4635692 14640590 0.7921 2574524
TOTAL 14640590 12698486




The Net Present Value at 6% discount rate is 2693588

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Payback Period
3. Internal Rate of Return
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Sciences Color.gilead shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Sciences Color.gilead have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Gilead Sciences, Inc.: Access Program

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Sales & Marketing Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Sciences Color.gilead often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Sciences Color.gilead needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10004898) -10004898 - -
Year 1 3469315 -6535583 3469315 0.8696 3016796
Year 2 3978017 -2557566 7447332 0.7561 3007952
Year 3 3942981 1385415 11390313 0.6575 2592574
Year 4 3250277 4635692 14640590 0.5718 1858356
TOTAL 10475678


The Net NPV after 4 years is 470780

(10475678 - 10004898 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10004898) -10004898 - -
Year 1 3469315 -6535583 3469315 0.8333 2891096
Year 2 3978017 -2557566 7447332 0.6944 2762512
Year 3 3942981 1385415 11390313 0.5787 2281818
Year 4 3250277 4635692 14640590 0.4823 1567456
TOTAL 9502881


The Net NPV after 4 years is -502017

At 20% discount rate the NPV is negative (9502881 - 10004898 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Sciences Color.gilead to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Sciences Color.gilead has a NPV value higher than Zero then finance managers at Sciences Color.gilead can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Sciences Color.gilead, then the stock price of the Sciences Color.gilead should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Sciences Color.gilead should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Gilead Sciences, Inc.: Access Program

References & Further Readings

V. Kasturi Rangan, Katharine Lee (2018), "Gilead Sciences, Inc.: Access Program Harvard Business Review Case Study. Published by HBR Publications.


Maxcom Telecom ADR SWOT Analysis / TOWS Matrix

Services , Communications Services


Shanghai Fortune Techgroup SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Coda Octopus SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Lowland SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Shagrir SWOT Analysis / TOWS Matrix

Services , Business Services


Matrix SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Main Street Capital SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Coset Inc SWOT Analysis / TOWS Matrix

Technology , Semiconductors


Superbag SWOT Analysis / TOWS Matrix

Basic Materials , Containers & Packaging


Pacific Century Premium SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Tenda SWOT Analysis / TOWS Matrix

Services , Real Estate Operations