At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Cabo San Viejo: Rewarding Loyalty case study is a Harvard Business School (HBR) case study written by Youngme Moon, Seth Schulman, Gail McGovern. The Cabo San Viejo: Rewarding Loyalty (referred as “Viejo Cabo” from here on) case study provides evaluation & decision scenario in field of Sales & Marketing. It also touches upon business topics such as - Value proposition, Risk management.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Cabo San Viejo: Rewarding Loyalty Case Study


In 2005, Cabo San Viejo, a premier health and fitness spa resort located in Palm Springs, California, is debating whether to introduce a Customer Rewards Program. Describes the customer management challenges the firm is facing and outlines the various ways in which a rewards program might be structured to help address those challenges.


Case Authors : Youngme Moon, Seth Schulman, Gail McGovern

Topic : Sales & Marketing

Related Areas : Risk management




Calculating Net Present Value (NPV) at 6% for Cabo San Viejo: Rewarding Loyalty Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10022657) -10022657 - -
Year 1 3470574 -6552083 3470574 0.9434 3274126
Year 2 3981948 -2570135 7452522 0.89 3543920
Year 3 3959231 1389096 11411753 0.8396 3324247
Year 4 3250361 4639457 14662114 0.7921 2574590
TOTAL 14662114 12716883




The Net Present Value at 6% discount rate is 2694226

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Profitability Index
3. Net Present Value
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Viejo Cabo have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Viejo Cabo shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Cabo San Viejo: Rewarding Loyalty

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Sales & Marketing Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Viejo Cabo often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Viejo Cabo needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10022657) -10022657 - -
Year 1 3470574 -6552083 3470574 0.8696 3017890
Year 2 3981948 -2570135 7452522 0.7561 3010925
Year 3 3959231 1389096 11411753 0.6575 2603259
Year 4 3250361 4639457 14662114 0.5718 1858404
TOTAL 10490478


The Net NPV after 4 years is 467821

(10490478 - 10022657 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10022657) -10022657 - -
Year 1 3470574 -6552083 3470574 0.8333 2892145
Year 2 3981948 -2570135 7452522 0.6944 2765242
Year 3 3959231 1389096 11411753 0.5787 2291222
Year 4 3250361 4639457 14662114 0.4823 1567497
TOTAL 9516105


The Net NPV after 4 years is -506552

At 20% discount rate the NPV is negative (9516105 - 10022657 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Viejo Cabo to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Viejo Cabo has a NPV value higher than Zero then finance managers at Viejo Cabo can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Viejo Cabo, then the stock price of the Viejo Cabo should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Viejo Cabo should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Cabo San Viejo: Rewarding Loyalty

References & Further Readings

Youngme Moon, Seth Schulman, Gail McGovern (2018), "Cabo San Viejo: Rewarding Loyalty Harvard Business Review Case Study. Published by HBR Publications.


Freni Brembo SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Parts


Rukun Raharja SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


Rosenblatt Gr SWOT Analysis / TOWS Matrix

Services , Personal Services


Samhwa Crown SWOT Analysis / TOWS Matrix

Basic Materials , Containers & Packaging


KS Energy Ltd SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


Auburn SWOT Analysis / TOWS Matrix

Financial , Regional Banks


One Liberty SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Atsugi Co Ltd SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories