Valuing Project Achieve Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Valuing Project Achieve case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Valuing Project Achieve case study is a Harvard Business School (HBR) case study written by Mihir A. Desai, Kathleen S. Luchs. The Valuing Project Achieve (referred as “Achieve Investors” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Financial management, Technology, Venture capital.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Valuing Project Achieve Case Study


Project Achieve is a start-up providing information management solutions for schools. Its founders see a need for software both to manage the volumes of information necessary to administer a school and to connect parents, teachers, and students in a more effective way. Originally funded by angel investors, Project Achieve is raising its first formal round of financing and needs to establish a firm valuation. This case outlines the economics of the business and provides the necessary background figures to build the business model and arrive at a valuation. Explores quantitative considerations of venture financing: 1) value neutrality of equity issuance is illustrated; 2) cost of capital is computed from raw return series, and the appropriate discount rate is selected based on comparables; 3) decision trees are used to highlight the importance of probabilistic thinking; and (4) subscriber models are compared with annual free cash flow models both for determining financial value and as decision-making tools for business choices. In addition, provides a setting to discuss the more qualitative issues involved in choosing investors. In particular, the founders are comparing two options: an infusion of additional capital from current and new investors or an investment from a potential strategic partner. Each option has very different implications for the direction of the business going forward.


Case Authors : Mihir A. Desai, Kathleen S. Luchs

Topic : Finance & Accounting

Related Areas : Financial management, Technology, Venture capital




Calculating Net Present Value (NPV) at 6% for Valuing Project Achieve Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10020745) -10020745 - -
Year 1 3459711 -6561034 3459711 0.9434 3263878
Year 2 3961916 -2599118 7421627 0.89 3526091
Year 3 3954041 1354923 11375668 0.8396 3319889
Year 4 3225298 4580221 14600966 0.7921 2554738
TOTAL 14600966 12664597




The Net Present Value at 6% discount rate is 2643852

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Net Present Value
3. Profitability Index
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Achieve Investors have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Achieve Investors shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Valuing Project Achieve

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Achieve Investors often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Achieve Investors needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10020745) -10020745 - -
Year 1 3459711 -6561034 3459711 0.8696 3008444
Year 2 3961916 -2599118 7421627 0.7561 2995778
Year 3 3954041 1354923 11375668 0.6575 2599846
Year 4 3225298 4580221 14600966 0.5718 1844075
TOTAL 10448143


The Net NPV after 4 years is 427398

(10448143 - 10020745 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10020745) -10020745 - -
Year 1 3459711 -6561034 3459711 0.8333 2883093
Year 2 3961916 -2599118 7421627 0.6944 2751331
Year 3 3954041 1354923 11375668 0.5787 2288218
Year 4 3225298 4580221 14600966 0.4823 1555410
TOTAL 9478051


The Net NPV after 4 years is -542694

At 20% discount rate the NPV is negative (9478051 - 10020745 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Achieve Investors to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Achieve Investors has a NPV value higher than Zero then finance managers at Achieve Investors can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Achieve Investors, then the stock price of the Achieve Investors should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Achieve Investors should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Valuing Project Achieve

References & Further Readings

Mihir A. Desai, Kathleen S. Luchs (2018), "Valuing Project Achieve Harvard Business Review Case Study. Published by HBR Publications.


Jianpu Tech SWOT Analysis / TOWS Matrix

Technology , Computer Services


Kokusai SWOT Analysis / TOWS Matrix

Technology , Scientific & Technical Instr.


Aiphone Co Ltd SWOT Analysis / TOWS Matrix

Technology , Communications Equipment


Mer SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Kis Wire SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Spice Mobility Ltd SWOT Analysis / TOWS Matrix

Technology , Communications Equipment


Anaplan SWOT Analysis / TOWS Matrix

Technology , Software & Programming


BNP Paribas SWOT Analysis / TOWS Matrix

Financial , Money Center Banks


CRE SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


nLIGHT SWOT Analysis / TOWS Matrix

Technology , Semiconductors


Nevada Iron SWOT Analysis / TOWS Matrix

Technology , Computer Services


Luxin Packing A SWOT Analysis / TOWS Matrix

Basic Materials , Containers & Packaging