Media Modeling and Budgeting at DMI Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Media Modeling and Budgeting at DMI case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Media Modeling and Budgeting at DMI case study is a Harvard Business School (HBR) case study written by Paul W. Farris, Phillip E. Pfeifer. The Media Modeling and Budgeting at DMI (referred as “Spending Carryover” from here on) case study provides evaluation & decision scenario in field of Sales & Marketing. It also touches upon business topics such as - Value proposition, Decision making, Marketing.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Media Modeling and Budgeting at DMI Case Study


A marketing director applies a scientific/quantitative approach to understanding and optimizing his company's marketing spending decisions. His hypotheses include the concepts of diminishing returns on spending, a results ceiling, carryover, and differential effectiveness. His team develops a mathematical formula that provides parameter estimates resulting from fitting the model to the three years of regional and national data. He must then decide how to apply the data to maximize media spending. A student Excel spreadsheet is available.


Case Authors : Paul W. Farris, Phillip E. Pfeifer

Topic : Sales & Marketing

Related Areas : Decision making, Marketing




Calculating Net Present Value (NPV) at 6% for Media Modeling and Budgeting at DMI Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10020776) -10020776 - -
Year 1 3450851 -6569925 3450851 0.9434 3255520
Year 2 3975359 -2594566 7426210 0.89 3538055
Year 3 3952021 1357455 11378231 0.8396 3318193
Year 4 3231530 4588985 14609761 0.7921 2559674
TOTAL 14609761 12671443




The Net Present Value at 6% discount rate is 2650667

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Net Present Value
3. Internal Rate of Return
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Spending Carryover shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Spending Carryover have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Media Modeling and Budgeting at DMI

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Sales & Marketing Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Spending Carryover often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Spending Carryover needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10020776) -10020776 - -
Year 1 3450851 -6569925 3450851 0.8696 3000740
Year 2 3975359 -2594566 7426210 0.7561 3005943
Year 3 3952021 1357455 11378231 0.6575 2598518
Year 4 3231530 4588985 14609761 0.5718 1847638
TOTAL 10452838


The Net NPV after 4 years is 432062

(10452838 - 10020776 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10020776) -10020776 - -
Year 1 3450851 -6569925 3450851 0.8333 2875709
Year 2 3975359 -2594566 7426210 0.6944 2760666
Year 3 3952021 1357455 11378231 0.5787 2287049
Year 4 3231530 4588985 14609761 0.4823 1558415
TOTAL 9481840


The Net NPV after 4 years is -538936

At 20% discount rate the NPV is negative (9481840 - 10020776 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Spending Carryover to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Spending Carryover has a NPV value higher than Zero then finance managers at Spending Carryover can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Spending Carryover, then the stock price of the Spending Carryover should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Spending Carryover should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Media Modeling and Budgeting at DMI

References & Further Readings

Paul W. Farris, Phillip E. Pfeifer (2018), "Media Modeling and Budgeting at DMI Harvard Business Review Case Study. Published by HBR Publications.


Bleecker SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Teikoku Tsushin Kogyo SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Ascent Solar SWOT Analysis / TOWS Matrix

Technology , Semiconductors


Scentre SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Kyobo BNK Special SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Honeywell SWOT Analysis / TOWS Matrix

Capital Goods , Aerospace & Defense


Sharps SWOT Analysis / TOWS Matrix

Services , Waste Management Services


Austal SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


Chongqing Gangjiu SWOT Analysis / TOWS Matrix

Transportation , Misc. Transportation