Modifying Merida: Disney's 11th Princess Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Modifying Merida: Disney's 11th Princess case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Modifying Merida: Disney's 11th Princess case study is a Harvard Business School (HBR) case study written by Matthew Thomson, Seung Hwan (Mark) Lee, Nicole Schaad. The Modifying Merida: Disney's 11th Princess (referred as “Image Viewing” from here on) case study provides evaluation & decision scenario in field of Sales & Marketing. It also touches upon business topics such as - Value proposition, .

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Modifying Merida: Disney's 11th Princess Case Study


When a well-known mass media corporation revises the image of a beloved and non-traditional movie character in a way that conforms to a physical stereotype, the female members of the viewing audience express their disapproval on a widespread scale. In the wake of the backlash, the company has a decision to make: Should it stick with the revised image, which has been deliberately redesigned to support an upcoming media campaign, or should it revert to the original image in order to appease the viewing public? The case presents both sides of the dilemma, revealing the psychological and commercial implications of using one image versus the other.


Case Authors : Matthew Thomson, Seung Hwan (Mark) Lee, Nicole Schaad

Topic : Sales & Marketing

Related Areas :




Calculating Net Present Value (NPV) at 6% for Modifying Merida: Disney's 11th Princess Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10010957) -10010957 - -
Year 1 3461803 -6549154 3461803 0.9434 3265852
Year 2 3959290 -2589864 7421093 0.89 3523754
Year 3 3971484 1381620 11392577 0.8396 3334535
Year 4 3243708 4625328 14636285 0.7921 2569321
TOTAL 14636285 12693461




The Net Present Value at 6% discount rate is 2682504

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Payback Period
3. Internal Rate of Return
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Image Viewing have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Image Viewing shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Modifying Merida: Disney's 11th Princess

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Sales & Marketing Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Image Viewing often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Image Viewing needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10010957) -10010957 - -
Year 1 3461803 -6549154 3461803 0.8696 3010263
Year 2 3959290 -2589864 7421093 0.7561 2993792
Year 3 3971484 1381620 11392577 0.6575 2611315
Year 4 3243708 4625328 14636285 0.5718 1854601
TOTAL 10469971


The Net NPV after 4 years is 459014

(10469971 - 10010957 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10010957) -10010957 - -
Year 1 3461803 -6549154 3461803 0.8333 2884836
Year 2 3959290 -2589864 7421093 0.6944 2749507
Year 3 3971484 1381620 11392577 0.5787 2298313
Year 4 3243708 4625328 14636285 0.4823 1564288
TOTAL 9496943


The Net NPV after 4 years is -514014

At 20% discount rate the NPV is negative (9496943 - 10010957 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Image Viewing to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Image Viewing has a NPV value higher than Zero then finance managers at Image Viewing can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Image Viewing, then the stock price of the Image Viewing should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Image Viewing should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Modifying Merida: Disney's 11th Princess

References & Further Readings

Matthew Thomson, Seung Hwan (Mark) Lee, Nicole Schaad (2018), "Modifying Merida: Disney's 11th Princess Harvard Business Review Case Study. Published by HBR Publications.


AgroFresh Solutions SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Realites SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Safran SWOT Analysis / TOWS Matrix

Capital Goods , Aerospace & Defense


Global Water SWOT Analysis / TOWS Matrix

Utilities , Water Utilities


BSL Ltd SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


HTG Molecular Diagnostics SWOT Analysis / TOWS Matrix

Technology , Scientific & Technical Instr.


Geodrill Ltd SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining


Goldstone SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver