Sheaffer International's BOOM Program Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Sheaffer International's BOOM Program case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Sheaffer International's BOOM Program case study is a Harvard Business School (HBR) case study written by Terry Anderson, J. Bishop Grewell. The Sheaffer International's BOOM Program (referred as “Sheaffer Boom” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Innovation, Marketing, Organizational structure, Risk management, Strategy execution, Sustainability.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Sheaffer International's BOOM Program Case Study


Jack Sheaffer had a unique wastewater treatment system that produced no organic sludge, no odor, and was cheaper than conventional systems. He was worried, however, that his business might suffer if there were a turndown in the marketplace. His previous business venture had failed when interest rates rose at the end of the 1970s. He wanted a business plan that would insulate him from marketplace shocks and found it with the BOOM program of build, own, operate, and maintain. BOOM put Sheaffer's company in charge of owning and maintaining the wastewater treatment systems designed by the company. It offered a steady source of income through long-term contracts with food processors, municipalities, and the like. A facility built on the North Fork of the Shenandoah River in northern Virginia would be BOOM's first test.


Case Authors : Terry Anderson, J. Bishop Grewell

Topic : Strategy & Execution

Related Areas : Innovation, Marketing, Organizational structure, Risk management, Strategy execution, Sustainability




Calculating Net Present Value (NPV) at 6% for Sheaffer International's BOOM Program Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10027089) -10027089 - -
Year 1 3466550 -6560539 3466550 0.9434 3270330
Year 2 3960486 -2600053 7427036 0.89 3524818
Year 3 3970453 1370400 11397489 0.8396 3333669
Year 4 3223917 4594317 14621406 0.7921 2553644
TOTAL 14621406 12682462




The Net Present Value at 6% discount rate is 2655373

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Net Present Value
3. Payback Period
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Sheaffer Boom have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Sheaffer Boom shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Sheaffer International's BOOM Program

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Sheaffer Boom often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Sheaffer Boom needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10027089) -10027089 - -
Year 1 3466550 -6560539 3466550 0.8696 3014391
Year 2 3960486 -2600053 7427036 0.7561 2994696
Year 3 3970453 1370400 11397489 0.6575 2610637
Year 4 3223917 4594317 14621406 0.5718 1843285
TOTAL 10463010


The Net NPV after 4 years is 435921

(10463010 - 10027089 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10027089) -10027089 - -
Year 1 3466550 -6560539 3466550 0.8333 2888792
Year 2 3960486 -2600053 7427036 0.6944 2750338
Year 3 3970453 1370400 11397489 0.5787 2297716
Year 4 3223917 4594317 14621406 0.4823 1554744
TOTAL 9491589


The Net NPV after 4 years is -535500

At 20% discount rate the NPV is negative (9491589 - 10027089 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Sheaffer Boom to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Sheaffer Boom has a NPV value higher than Zero then finance managers at Sheaffer Boom can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Sheaffer Boom, then the stock price of the Sheaffer Boom should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Sheaffer Boom should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Sheaffer International's BOOM Program

References & Further Readings

Terry Anderson, J. Bishop Grewell (2018), "Sheaffer International's BOOM Program Harvard Business Review Case Study. Published by HBR Publications.


SDIC Essence Holdings SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


Arcontech SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Hunan Tyen Machinery B SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Parts


Unidus SWOT Analysis / TOWS Matrix

Basic Materials , Fabricated Plastic & Rubber


Kiddieland International SWOT Analysis / TOWS Matrix

Consumer Cyclical , Recreational Products


Korea Cast Pip SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


ALD SWOT Analysis / TOWS Matrix

Services , Rental & Leasing


Gayatri Projects SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


LDK Solar SWOT Analysis / TOWS Matrix

Technology , Semiconductors


Ten Entertainment SWOT Analysis / TOWS Matrix

Services , Recreational Activities