CSIRO: The Light Metals Flagship Decision Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for CSIRO: The Light Metals Flagship Decision case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. CSIRO: The Light Metals Flagship Decision case study is a Harvard Business School (HBR) case study written by Willy Shih, Margaret Pierson, Dawn Lau. The CSIRO: The Light Metals Flagship Decision (referred as “Csiro Metals” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Globalization, Growth strategy, IT, Manufacturing, Research & development.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of CSIRO: The Light Metals Flagship Decision Case Study


This case explores the challenge of investing in basic research as a public good. CSIRO was Australia's leading science and research agency, and it was chartered to enhance national prosperity through R&D. Its Flagships program was designed to align research interests with national priorities, with a strong focus on the adoption of research outputs. The Light Metals Flagship (LMF) was one of six flagships established in 2003, and its goal was to help the nation capture more of the added value of its resources by developing and commercializing downstream technologies in the processing and fabrication of products made from aluminum, magnesium, and titanium. While the LMF met with technical successes, Australian industry was reticent to co-invest. This lack of industry enthusiasm was in many ways unsurprising, as governments often found it important to fund long-term basic research that was outside of the horizon of firms. But what kind of a signal would stopping the program send? Was CSIRO prepared to let short-term thinking in light metals firms drive its agenda? The case examines the technical decision-making process.


Case Authors : Willy Shih, Margaret Pierson, Dawn Lau

Topic : Strategy & Execution

Related Areas : Globalization, Growth strategy, IT, Manufacturing, Research & development




Calculating Net Present Value (NPV) at 6% for CSIRO: The Light Metals Flagship Decision Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10025270) -10025270 - -
Year 1 3445960 -6579310 3445960 0.9434 3250906
Year 2 3963730 -2615580 7409690 0.89 3527706
Year 3 3963489 1347909 11373179 0.8396 3327822
Year 4 3248259 4596168 14621438 0.7921 2572925
TOTAL 14621438 12679358




The Net Present Value at 6% discount rate is 2654088

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Net Present Value
3. Internal Rate of Return
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Csiro Metals have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Csiro Metals shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of CSIRO: The Light Metals Flagship Decision

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Csiro Metals often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Csiro Metals needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10025270) -10025270 - -
Year 1 3445960 -6579310 3445960 0.8696 2996487
Year 2 3963730 -2615580 7409690 0.7561 2997149
Year 3 3963489 1347909 11373179 0.6575 2606058
Year 4 3248259 4596168 14621438 0.5718 1857203
TOTAL 10456897


The Net NPV after 4 years is 431627

(10456897 - 10025270 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10025270) -10025270 - -
Year 1 3445960 -6579310 3445960 0.8333 2871633
Year 2 3963730 -2615580 7409690 0.6944 2752590
Year 3 3963489 1347909 11373179 0.5787 2293686
Year 4 3248259 4596168 14621438 0.4823 1566483
TOTAL 9484392


The Net NPV after 4 years is -540878

At 20% discount rate the NPV is negative (9484392 - 10025270 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Csiro Metals to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Csiro Metals has a NPV value higher than Zero then finance managers at Csiro Metals can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Csiro Metals, then the stock price of the Csiro Metals should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Csiro Metals should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of CSIRO: The Light Metals Flagship Decision

References & Further Readings

Willy Shih, Margaret Pierson, Dawn Lau (2018), "CSIRO: The Light Metals Flagship Decision Harvard Business Review Case Study. Published by HBR Publications.


Moly Mines SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining


Gillette India SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Personal & Household Prods.


Jinguyuan Hold A SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver


Lai Sun Develop SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Alphabet A SWOT Analysis / TOWS Matrix

Technology , Computer Services


Quick Co Ltd SWOT Analysis / TOWS Matrix

Services , Business Services


Moller Maersk A SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


Labixiaoxin Snacks SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


ATN Int SWOT Analysis / TOWS Matrix

Services , Communications Services