eStore at Shell Canada Limited Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for eStore at Shell Canada Limited case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. eStore at Shell Canada Limited case study is a Harvard Business School (HBR) case study written by Deborah Compeau, Barbara Marcolin, Carol Saunders, Chad Saunders. The eStore at Shell Canada Limited (referred as “Estore Eproducts” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Strategy.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of eStore at Shell Canada Limited Case Study


The commercial eProducts manager at Shell Canada has to determine how to improve the adoption and utilization of their eCommerce channel. eStore had been developed for the fuel and lubricants market as a pilot test of how Shell might communicate with its customers electronically, thus reducing costs. While eStore had been in place for a year, and many customers had signed up, utilization was low. A consulting firm has made recommendations about the technical issues that might be driving low utilization. The commercial eProducts manager has to consider whether the problems are purely technical and make a recommendation on how to proceed.


Case Authors : Deborah Compeau, Barbara Marcolin, Carol Saunders, Chad Saunders

Topic : Strategy & Execution

Related Areas : Strategy




Calculating Net Present Value (NPV) at 6% for eStore at Shell Canada Limited Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10017033) -10017033 - -
Year 1 3461820 -6555213 3461820 0.9434 3265868
Year 2 3959696 -2595517 7421516 0.89 3524115
Year 3 3956866 1361349 11378382 0.8396 3322261
Year 4 3247394 4608743 14625776 0.7921 2572240
TOTAL 14625776 12684484




The Net Present Value at 6% discount rate is 2667451

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Net Present Value
3. Profitability Index
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Estore Eproducts shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Estore Eproducts have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of eStore at Shell Canada Limited

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Estore Eproducts often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Estore Eproducts needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10017033) -10017033 - -
Year 1 3461820 -6555213 3461820 0.8696 3010278
Year 2 3959696 -2595517 7421516 0.7561 2994099
Year 3 3956866 1361349 11378382 0.6575 2601704
Year 4 3247394 4608743 14625776 0.5718 1856708
TOTAL 10462789


The Net NPV after 4 years is 445756

(10462789 - 10017033 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10017033) -10017033 - -
Year 1 3461820 -6555213 3461820 0.8333 2884850
Year 2 3959696 -2595517 7421516 0.6944 2749789
Year 3 3956866 1361349 11378382 0.5787 2289853
Year 4 3247394 4608743 14625776 0.4823 1566066
TOTAL 9490558


The Net NPV after 4 years is -526475

At 20% discount rate the NPV is negative (9490558 - 10017033 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Estore Eproducts to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Estore Eproducts has a NPV value higher than Zero then finance managers at Estore Eproducts can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Estore Eproducts, then the stock price of the Estore Eproducts should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Estore Eproducts should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of eStore at Shell Canada Limited

References & Further Readings

Deborah Compeau, Barbara Marcolin, Carol Saunders, Chad Saunders (2018), "eStore at Shell Canada Limited Harvard Business Review Case Study. Published by HBR Publications.


Flexigroup SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services


Duta Anggada SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Niigata Kotsu SWOT Analysis / TOWS Matrix

Transportation , Misc. Transportation


Changan Auto A SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Manufacturers


Assystem SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Nextgen SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Mercury Industries Bhd SWOT Analysis / TOWS Matrix

Basic Materials , Chemical Manufacturing


Meisheng Cultural & Creative SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


Altisource Portfolio Solutions SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services