THE PARKING FACILITY VENTURE - General Instructions Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for THE PARKING FACILITY VENTURE - General Instructions case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. THE PARKING FACILITY VENTURE - General Instructions case study is a Harvard Business School (HBR) case study written by Program on Negotiation. The THE PARKING FACILITY VENTURE - General Instructions (referred as “Parking Firms” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Influence, Negotiations, Policy.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of THE PARKING FACILITY VENTURE - General Instructions Case Study


Three-party scoreable negotiation among three firms regarding the joint construction of an off-street parking facility. Three firms (Arundel Products, Bartel Publishing and Chiptech) are building new facilities in a recently developed part of town. The city requires each of them to construct off-street parking for their employees. The firms have jointly hired financial analysts, architects and other specialists to describe and price their options. The firms recognize that if they pool their capital and operating resources, they can build one parking garage to serve all employees. However, if all three firms cannot come to an agreement, various joint ventures between any two of the firms would still save some money for the two participants, though not as much. The climate for coalitions are unstable because the goal of each company is to maximize its own interests and financial well-being. This is a role play case.


Case Authors : Program on Negotiation

Topic : Strategy & Execution

Related Areas : Influence, Negotiations, Policy




Calculating Net Present Value (NPV) at 6% for THE PARKING FACILITY VENTURE - General Instructions Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10028611) -10028611 - -
Year 1 3457726 -6570885 3457726 0.9434 3262006
Year 2 3979137 -2591748 7436863 0.89 3541418
Year 3 3955840 1364092 11392703 0.8396 3321400
Year 4 3228725 4592817 14621428 0.7921 2557453
TOTAL 14621428 12682276




The Net Present Value at 6% discount rate is 2653665

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Profitability Index
3. Internal Rate of Return
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Parking Firms have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Parking Firms shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of THE PARKING FACILITY VENTURE - General Instructions

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Parking Firms often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Parking Firms needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10028611) -10028611 - -
Year 1 3457726 -6570885 3457726 0.8696 3006718
Year 2 3979137 -2591748 7436863 0.7561 3008799
Year 3 3955840 1364092 11392703 0.6575 2601029
Year 4 3228725 4592817 14621428 0.5718 1846034
TOTAL 10462581


The Net NPV after 4 years is 433970

(10462581 - 10028611 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10028611) -10028611 - -
Year 1 3457726 -6570885 3457726 0.8333 2881438
Year 2 3979137 -2591748 7436863 0.6944 2763290
Year 3 3955840 1364092 11392703 0.5787 2289259
Year 4 3228725 4592817 14621428 0.4823 1557063
TOTAL 9491050


The Net NPV after 4 years is -537561

At 20% discount rate the NPV is negative (9491050 - 10028611 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Parking Firms to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Parking Firms has a NPV value higher than Zero then finance managers at Parking Firms can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Parking Firms, then the stock price of the Parking Firms should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Parking Firms should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of THE PARKING FACILITY VENTURE - General Instructions

References & Further Readings

Program on Negotiation (2018), "THE PARKING FACILITY VENTURE - General Instructions Harvard Business Review Case Study. Published by HBR Publications.


eBASE SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Imbalie Beauty SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Personal & Household Prods.


Essex Property SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Impression Healthcare SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Deutsche Wohnen SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Sihuan Bioeng A SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Optimus Group SWOT Analysis / TOWS Matrix

Services , Retail (Specialty)


Tibet Mineral A SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining


Danel SWOT Analysis / TOWS Matrix

Services , Business Services


European Lithium SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining