Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Retail Financial Services in 1998: First Union case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Retail Financial Services in 1998: First Union case study is a Harvard Business School (HBR) case study written by Stephen P. Bradley, Takia Mahmood. The Retail Financial Services in 1998: First Union (referred as “Retail 1998” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Financial markets, Reorganization.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Retail Financial Services in 1998: First Union Case Study


Provides an overview of First Union's current strategy for retail financial services. Retail Financial Services in 1998 should be given to all students as background material. The class should then be split into groups, with each group receiving one of the following cases: Retail Financial Services in 1998: Charles Schwab, Retail Financial Services in 1998: Fidelity Investments, Retail Financial Services in 1998: First Union, Retail Financial Services in 1998: Merrill Lynch, or Retail Financial Services in 1998: Travelers to prepare in order to understand how each player is attempting to capture value in the converging world of retail financial services.


Case Authors : Stephen P. Bradley, Takia Mahmood

Topic : Strategy & Execution

Related Areas : Financial markets, Reorganization




Calculating Net Present Value (NPV) at 6% for Retail Financial Services in 1998: First Union Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10019932) -10019932 - -
Year 1 3472545 -6547387 3472545 0.9434 3275986
Year 2 3957314 -2590073 7429859 0.89 3521995
Year 3 3970327 1380254 11400186 0.8396 3333563
Year 4 3238444 4618698 14638630 0.7921 2565151
TOTAL 14638630 12696695




The Net Present Value at 6% discount rate is 2676763

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Profitability Index
3. Internal Rate of Return
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Retail 1998 have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Retail 1998 shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Retail Financial Services in 1998: First Union

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Retail 1998 often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Retail 1998 needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10019932) -10019932 - -
Year 1 3472545 -6547387 3472545 0.8696 3019604
Year 2 3957314 -2590073 7429859 0.7561 2992298
Year 3 3970327 1380254 11400186 0.6575 2610554
Year 4 3238444 4618698 14638630 0.5718 1851591
TOTAL 10474048


The Net NPV after 4 years is 454116

(10474048 - 10019932 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10019932) -10019932 - -
Year 1 3472545 -6547387 3472545 0.8333 2893788
Year 2 3957314 -2590073 7429859 0.6944 2748135
Year 3 3970327 1380254 11400186 0.5787 2297643
Year 4 3238444 4618698 14638630 0.4823 1561750
TOTAL 9501315


The Net NPV after 4 years is -518617

At 20% discount rate the NPV is negative (9501315 - 10019932 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Retail 1998 to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Retail 1998 has a NPV value higher than Zero then finance managers at Retail 1998 can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Retail 1998, then the stock price of the Retail 1998 should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Retail 1998 should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Retail Financial Services in 1998: First Union

References & Further Readings

Stephen P. Bradley, Takia Mahmood (2018), "Retail Financial Services in 1998: First Union Harvard Business Review Case Study. Published by HBR Publications.


Rainbow Store A SWOT Analysis / TOWS Matrix

Services , Retail (Department & Discount)


Device ENG SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Adventa SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Danfu Compressor A SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


Malaysian Bulk Carriers SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


Bunge Pref SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Citycon Oyj SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Ls Networks SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


Hongda Xingye A SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber


NCsoft Corp SWOT Analysis / TOWS Matrix

Technology , Computer Services