IMAX (B): Ten Years with DMR Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for IMAX (B): Ten Years with DMR case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. IMAX (B): Ten Years with DMR case study is a Harvard Business School (HBR) case study written by Metin Sengul, Alexander T. Venino, Javier Gimeno. The IMAX (B): Ten Years with DMR (referred as “Dmr Imax” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, .

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of IMAX (B): Ten Years with DMR Case Study


Case A reviews the history of IMAX Corporation from its founding until the introduction of Digital Media Remastering (DMR) technology in 2002. Since its founding, IMAX had struggled to achieve sustainable, profitable growth. The case explores IMAX's difficulties in attracting movie studios and theatres to its platform. Case B describes the changes in the ecosystem implemented after DMR, and the resulting performance.


Case Authors : Metin Sengul, Alexander T. Venino, Javier Gimeno

Topic : Strategy & Execution

Related Areas :




Calculating Net Present Value (NPV) at 6% for IMAX (B): Ten Years with DMR Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10022404) -10022404 - -
Year 1 3453614 -6568790 3453614 0.9434 3258126
Year 2 3968674 -2600116 7422288 0.89 3532106
Year 3 3970154 1370038 11392442 0.8396 3333418
Year 4 3228487 4598525 14620929 0.7921 2557264
TOTAL 14620929 12680914




The Net Present Value at 6% discount rate is 2658510

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Net Present Value
3. Internal Rate of Return
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Dmr Imax shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Dmr Imax have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of IMAX (B): Ten Years with DMR

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Dmr Imax often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Dmr Imax needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10022404) -10022404 - -
Year 1 3453614 -6568790 3453614 0.8696 3003143
Year 2 3968674 -2600116 7422288 0.7561 3000888
Year 3 3970154 1370038 11392442 0.6575 2610441
Year 4 3228487 4598525 14620929 0.5718 1845898
TOTAL 10460369


The Net NPV after 4 years is 437965

(10460369 - 10022404 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10022404) -10022404 - -
Year 1 3453614 -6568790 3453614 0.8333 2878012
Year 2 3968674 -2600116 7422288 0.6944 2756024
Year 3 3970154 1370038 11392442 0.5787 2297543
Year 4 3228487 4598525 14620929 0.4823 1556948
TOTAL 9488526


The Net NPV after 4 years is -533878

At 20% discount rate the NPV is negative (9488526 - 10022404 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Dmr Imax to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Dmr Imax has a NPV value higher than Zero then finance managers at Dmr Imax can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Dmr Imax, then the stock price of the Dmr Imax should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Dmr Imax should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of IMAX (B): Ten Years with DMR

References & Further Readings

Metin Sengul, Alexander T. Venino, Javier Gimeno (2018), "IMAX (B): Ten Years with DMR Harvard Business Review Case Study. Published by HBR Publications.


Valor Co Ltd SWOT Analysis / TOWS Matrix

Services , Retail (Grocery)


Sanofi SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Nobilis Health Corp SWOT Analysis / TOWS Matrix

Healthcare , Healthcare Facilities


Hoifu Energy SWOT Analysis / TOWS Matrix

Energy , Oil & Gas Operations


Genmab SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Bluefire SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


Mac House SWOT Analysis / TOWS Matrix

Services , Retail (Apparel)


Cross Country SWOT Analysis / TOWS Matrix

Services , Business Services


Koryojyuhan SWOT Analysis / TOWS Matrix

Services , Real Estate Operations