×




ezBoard: Making Customers Pay, Robert Labatt, CEO Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for ezBoard: Making Customers Pay, Robert Labatt, CEO case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. ezBoard: Making Customers Pay, Robert Labatt, CEO case study is a Harvard Business School (HBR) case study written by Brian V. Viard, Pamela Yatsko. The ezBoard: Making Customers Pay, Robert Labatt, CEO (referred as “Labatt Ezboard” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Marketing, Pricing.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of ezBoard: Making Customers Pay, Robert Labatt, CEO Case Study


When Robert Labatt took over ezboard's helm in 2004, he faced a quandary: How to turn the company's essentially free information product into a paid product that would earn enough revenue to satisfy ezboard's increasingly impatient investors? In this classroom video, Labatt discusses strategy, including a revenue model, user hierarchy, and the role of advertising. He talks about his goals as CEO and the pressures that he faces. This video is intended to be used in conjunction with the written case SM172 ezboard: Making Customers Pay. http://www.gsb.stanford.edu/multimedia/flv/100618-Case-EZboardTlr.html


Case Authors : Brian V. Viard, Pamela Yatsko

Topic : Strategy & Execution

Related Areas : Marketing, Pricing




Calculating Net Present Value (NPV) at 6% for ezBoard: Making Customers Pay, Robert Labatt, CEO Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10018875) -10018875 - -
Year 1 3444230 -6574645 3444230 0.9434 3249274
Year 2 3971348 -2603297 7415578 0.89 3534486
Year 3 3942763 1339466 11358341 0.8396 3310420
Year 4 3248247 4587713 14606588 0.7921 2572916
TOTAL 14606588 12667095




The Net Present Value at 6% discount rate is 2648220

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Profitability Index
3. Internal Rate of Return
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Labatt Ezboard have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Labatt Ezboard shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of ezBoard: Making Customers Pay, Robert Labatt, CEO

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Labatt Ezboard often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Labatt Ezboard needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10018875) -10018875 - -
Year 1 3444230 -6574645 3444230 0.8696 2994983
Year 2 3971348 -2603297 7415578 0.7561 3002910
Year 3 3942763 1339466 11358341 0.6575 2592431
Year 4 3248247 4587713 14606588 0.5718 1857196
TOTAL 10447519


The Net NPV after 4 years is 428644

(10447519 - 10018875 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10018875) -10018875 - -
Year 1 3444230 -6574645 3444230 0.8333 2870192
Year 2 3971348 -2603297 7415578 0.6944 2757881
Year 3 3942763 1339466 11358341 0.5787 2281692
Year 4 3248247 4587713 14606588 0.4823 1566477
TOTAL 9476241


The Net NPV after 4 years is -542634

At 20% discount rate the NPV is negative (9476241 - 10018875 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Labatt Ezboard to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Labatt Ezboard has a NPV value higher than Zero then finance managers at Labatt Ezboard can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Labatt Ezboard, then the stock price of the Labatt Ezboard should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Labatt Ezboard should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of ezBoard: Making Customers Pay, Robert Labatt, CEO

References & Further Readings

Brian V. Viard, Pamela Yatsko (2018), "ezBoard: Making Customers Pay, Robert Labatt, CEO Harvard Business Review Case Study. Published by HBR Publications.


Linewell Software SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Centrotec SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


AGCO SWOT Analysis / TOWS Matrix

Capital Goods , Constr. & Agric. Machinery


Cas SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


Sanwaria Agro Oils Ltd SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Lombard Et Medot SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Beverages (Alcoholic)


Software Service SWOT Analysis / TOWS Matrix

Technology , Computer Services


Christian Dior SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


Nano Dimension SWOT Analysis / TOWS Matrix

Technology , Computer Peripherals