Novo Industri Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Novo Industri case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Novo Industri case study is a Harvard Business School (HBR) case study written by Michael E. Porter, Michael J. Enright. The Novo Industri (referred as “Novo Novo's” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Joint ventures, Marketing.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Novo Industri Case Study


Describes the structure of the insulin industry, a treatment for diabetes and Novo's strategy and competitive position in early 1982. The industry is undergoing significant change and Novo must decide how to defend and build its international position. Designed as an early case in global strategy. The class can understand how Novo has competed internationally in the past, how that relates to industry structure, and how industry changes will alter the appropriate way of competing globally. Coalitions of alliances factor into the list of strategic alternatives.


Case Authors : Michael E. Porter, Michael J. Enright

Topic : Strategy & Execution

Related Areas : Joint ventures, Marketing




Calculating Net Present Value (NPV) at 6% for Novo Industri Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10005578) -10005578 - -
Year 1 3452661 -6552917 3452661 0.9434 3257227
Year 2 3979905 -2573012 7432566 0.89 3542101
Year 3 3960069 1387057 11392635 0.8396 3324950
Year 4 3251657 4638714 14644292 0.7921 2575617
TOTAL 14644292 12699896




The Net Present Value at 6% discount rate is 2694318

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Net Present Value
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Novo Novo's have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Novo Novo's shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Novo Industri

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Novo Novo's often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Novo Novo's needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10005578) -10005578 - -
Year 1 3452661 -6552917 3452661 0.8696 3002314
Year 2 3979905 -2573012 7432566 0.7561 3009380
Year 3 3960069 1387057 11392635 0.6575 2603810
Year 4 3251657 4638714 14644292 0.5718 1859145
TOTAL 10474649


The Net NPV after 4 years is 469071

(10474649 - 10005578 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10005578) -10005578 - -
Year 1 3452661 -6552917 3452661 0.8333 2877218
Year 2 3979905 -2573012 7432566 0.6944 2763823
Year 3 3960069 1387057 11392635 0.5787 2291707
Year 4 3251657 4638714 14644292 0.4823 1568122
TOTAL 9500869


The Net NPV after 4 years is -504709

At 20% discount rate the NPV is negative (9500869 - 10005578 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Novo Novo's to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Novo Novo's has a NPV value higher than Zero then finance managers at Novo Novo's can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Novo Novo's, then the stock price of the Novo Novo's should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Novo Novo's should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Novo Industri

References & Further Readings

Michael E. Porter, Michael J. Enright (2018), "Novo Industri Harvard Business Review Case Study. Published by HBR Publications.


Precision Tsugami SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


NFK SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


FTE Networks SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Northstar Global SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Hanwha Chemical Pref SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber


Jincheng Paper A SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Neopost SWOT Analysis / TOWS Matrix

Technology , Office Equipment


StoneCo SWOT Analysis / TOWS Matrix

Technology , Software & Programming