Amazon.com (in 2013): Will Amazon Kindle Another Fire? Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Amazon.com (in 2013): Will Amazon Kindle Another Fire? case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Amazon.com (in 2013): Will Amazon Kindle Another Fire? case study is a Harvard Business School (HBR) case study written by Frank T. Rothaermel, Seth Taylor, Marne L. Arthaud-Day. The Amazon.com (in 2013): Will Amazon Kindle Another Fire? (referred as “Kindle Bezos” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Innovation, Leadership.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Amazon.com (in 2013): Will Amazon Kindle Another Fire? Case Study


The case is written from the perspective of Jeff Bezos, CEO of Amazon.com, as he ponders the company's strategy over the next several years. At one point, Bezos believed there was room in the marketplace for the Kindle as a dedicated e-reader alongside tablets and laptops. Since its introduction in 2010, however, Apple's iPad has become the all-in-one vehicle for digital content, and competition in the mobile device industry has risen sharply.


Case Authors : Frank T. Rothaermel, Seth Taylor, Marne L. Arthaud-Day

Topic : Strategy & Execution

Related Areas : Innovation, Leadership




Calculating Net Present Value (NPV) at 6% for Amazon.com (in 2013): Will Amazon Kindle Another Fire? Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10008989) -10008989 - -
Year 1 3443512 -6565477 3443512 0.9434 3248596
Year 2 3963078 -2602399 7406590 0.89 3527125
Year 3 3965610 1363211 11372200 0.8396 3329603
Year 4 3225129 4588340 14597329 0.7921 2554604
TOTAL 14597329 12659928




The Net Present Value at 6% discount rate is 2650939

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Internal Rate of Return
3. Net Present Value
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Kindle Bezos have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Kindle Bezos shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Amazon.com (in 2013): Will Amazon Kindle Another Fire?

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Kindle Bezos often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Kindle Bezos needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10008989) -10008989 - -
Year 1 3443512 -6565477 3443512 0.8696 2994358
Year 2 3963078 -2602399 7406590 0.7561 2996656
Year 3 3965610 1363211 11372200 0.6575 2607453
Year 4 3225129 4588340 14597329 0.5718 1843978
TOTAL 10442446


The Net NPV after 4 years is 433457

(10442446 - 10008989 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10008989) -10008989 - -
Year 1 3443512 -6565477 3443512 0.8333 2869593
Year 2 3963078 -2602399 7406590 0.6944 2752138
Year 3 3965610 1363211 11372200 0.5787 2294913
Year 4 3225129 4588340 14597329 0.4823 1555328
TOTAL 9471972


The Net NPV after 4 years is -537017

At 20% discount rate the NPV is negative (9471972 - 10008989 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Kindle Bezos to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Kindle Bezos has a NPV value higher than Zero then finance managers at Kindle Bezos can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Kindle Bezos, then the stock price of the Kindle Bezos should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Kindle Bezos should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Amazon.com (in 2013): Will Amazon Kindle Another Fire?

References & Further Readings

Frank T. Rothaermel, Seth Taylor, Marne L. Arthaud-Day (2018), "Amazon.com (in 2013): Will Amazon Kindle Another Fire? Harvard Business Review Case Study. Published by HBR Publications.


CESP ON SWOT Analysis / TOWS Matrix

Utilities , Electric Utilities


Phoenix Media Invest SWOT Analysis / TOWS Matrix

Services , Broadcasting & Cable TV


Lonmin SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining


Advicenne SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Dongfeng Motor Group Co SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Manufacturers


Datagroup SWOT Analysis / TOWS Matrix

Technology , Computer Services


Amkor SWOT Analysis / TOWS Matrix

Technology , Semiconductors


Lepu Medical Tech Beijing SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Lowe’s SWOT Analysis / TOWS Matrix

Services , Retail (Home Improvement)