AEROSPACE INVESTMENT: BALANCING VENTURE & RELATIONSHIP CAPITAL - Confidential Instructions for the Venture Capitalist Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for AEROSPACE INVESTMENT: BALANCING VENTURE & RELATIONSHIP CAPITAL - Confidential Instructions for the Venture Capitalist case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. AEROSPACE INVESTMENT: BALANCING VENTURE & RELATIONSHIP CAPITAL - Confidential Instructions for the Venture Capitalist case study is a Harvard Business School (HBR) case study written by Nicholas Sabin. The AEROSPACE INVESTMENT: BALANCING VENTURE & RELATIONSHIP CAPITAL - Confidential Instructions for the Venture Capitalist (referred as “Capitalist Aerovent” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Negotiations, Venture capital.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of AEROSPACE INVESTMENT: BALANCING VENTURE & RELATIONSHIP CAPITAL - Confidential Instructions for the Venture Capitalist Case Study


Confidential Instructions for the Venture Capitalist for PON023.Two-party term sheet negotiation between a venture capitalist and the founder of an aerospace start-up company in which participants are scored both on their substantive performance and on the other party's perception of the relationship. The venture capital (VC) firm Aerovent Capital is considering a $100 million investment in the startup company Earth Escape. The founder of Earth Escape and the lead partner from Aerovent Capital must negotiate a term sheet outlining eight significant terms of the investment. Both parties are concerned with structuring a deal that protects their substantive investment interests and with creating a positive foundation for their potential collaboration. The simulation introduces the incorporation of process and relationship interests into negotiation strategy. This is a role play case.


Case Authors : Nicholas Sabin

Topic : Strategy & Execution

Related Areas : Negotiations, Venture capital




Calculating Net Present Value (NPV) at 6% for AEROSPACE INVESTMENT: BALANCING VENTURE & RELATIONSHIP CAPITAL - Confidential Instructions for the Venture Capitalist Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10001573) -10001573 - -
Year 1 3447913 -6553660 3447913 0.9434 3252748
Year 2 3960694 -2592966 7408607 0.89 3525004
Year 3 3940991 1348025 11349598 0.8396 3308932
Year 4 3224746 4572771 14574344 0.7921 2554301
TOTAL 14574344 12640985




The Net Present Value at 6% discount rate is 2639412

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Payback Period
3. Internal Rate of Return
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Capitalist Aerovent shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Capitalist Aerovent have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of AEROSPACE INVESTMENT: BALANCING VENTURE & RELATIONSHIP CAPITAL - Confidential Instructions for the Venture Capitalist

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Capitalist Aerovent often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Capitalist Aerovent needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10001573) -10001573 - -
Year 1 3447913 -6553660 3447913 0.8696 2998185
Year 2 3960694 -2592966 7408607 0.7561 2994854
Year 3 3940991 1348025 11349598 0.6575 2591266
Year 4 3224746 4572771 14574344 0.5718 1843759
TOTAL 10428063


The Net NPV after 4 years is 426490

(10428063 - 10001573 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10001573) -10001573 - -
Year 1 3447913 -6553660 3447913 0.8333 2873261
Year 2 3960694 -2592966 7408607 0.6944 2750482
Year 3 3940991 1348025 11349598 0.5787 2280666
Year 4 3224746 4572771 14574344 0.4823 1555144
TOTAL 9459553


The Net NPV after 4 years is -542020

At 20% discount rate the NPV is negative (9459553 - 10001573 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Capitalist Aerovent to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Capitalist Aerovent has a NPV value higher than Zero then finance managers at Capitalist Aerovent can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Capitalist Aerovent, then the stock price of the Capitalist Aerovent should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Capitalist Aerovent should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of AEROSPACE INVESTMENT: BALANCING VENTURE & RELATIONSHIP CAPITAL - Confidential Instructions for the Venture Capitalist

References & Further Readings

Nicholas Sabin (2018), "AEROSPACE INVESTMENT: BALANCING VENTURE & RELATIONSHIP CAPITAL - Confidential Instructions for the Venture Capitalist Harvard Business Review Case Study. Published by HBR Publications.


Auplata SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver


Mansion International SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


Gastar Pref A SWOT Analysis / TOWS Matrix

Energy , Oil & Gas - Integrated


Magyar Telekom Plc SWOT Analysis / TOWS Matrix

Services , Communications Services


Novume SWOT Analysis / TOWS Matrix

Services , Business Services


Les Trois Chenes SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Kerry Group SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Snap SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Exa E&C SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Essential Innovation SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services