Maytag Corp.--2002 Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Maytag Corp.--2002 case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Maytag Corp.--2002 case study is a Harvard Business School (HBR) case study written by Suzanne Allen, Stephen Allen. The Maytag Corp.--2002 (referred as “Maytag Period” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Globalization, Strategy execution.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Maytag Corp.--2002 Case Study


Summarizes the events, decisions, and results at the firm during the period 1986 to 2002. The key issues involve the financial goals of Maytag during this period, its inability to reach them, and the likely reasons for such a failure. Maytag seemed to suffer from both strategy formulation as well as strategy implementation problems. The structural evolution of the industry had not made the strategy task any easier for Maytag during this period. The open question is how Maytag would fare in the future and what its senior managers should do.


Case Authors : Suzanne Allen, Stephen Allen

Topic : Strategy & Execution

Related Areas : Globalization, Strategy execution




Calculating Net Present Value (NPV) at 6% for Maytag Corp.--2002 Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10012632) -10012632 - -
Year 1 3457590 -6555042 3457590 0.9434 3261877
Year 2 3967400 -2587642 7424990 0.89 3530972
Year 3 3970100 1382458 11395090 0.8396 3333373
Year 4 3230507 4612965 14625597 0.7921 2558864
TOTAL 14625597 12685086




The Net Present Value at 6% discount rate is 2672454

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Profitability Index
3. Net Present Value
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Maytag Period have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Maytag Period shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Maytag Corp.--2002

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Maytag Period often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Maytag Period needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10012632) -10012632 - -
Year 1 3457590 -6555042 3457590 0.8696 3006600
Year 2 3967400 -2587642 7424990 0.7561 2999924
Year 3 3970100 1382458 11395090 0.6575 2610405
Year 4 3230507 4612965 14625597 0.5718 1847053
TOTAL 10463982


The Net NPV after 4 years is 451350

(10463982 - 10012632 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10012632) -10012632 - -
Year 1 3457590 -6555042 3457590 0.8333 2881325
Year 2 3967400 -2587642 7424990 0.6944 2755139
Year 3 3970100 1382458 11395090 0.5787 2297512
Year 4 3230507 4612965 14625597 0.4823 1557922
TOTAL 9491897


The Net NPV after 4 years is -520735

At 20% discount rate the NPV is negative (9491897 - 10012632 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Maytag Period to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Maytag Period has a NPV value higher than Zero then finance managers at Maytag Period can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Maytag Period, then the stock price of the Maytag Period should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Maytag Period should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Maytag Corp.--2002

References & Further Readings

Suzanne Allen, Stephen Allen (2018), "Maytag Corp.--2002 Harvard Business Review Case Study. Published by HBR Publications.


COTEMINAS SWOT Analysis / TOWS Matrix

Consumer Cyclical , Textiles - Non Apparel


Dilip Buildcon SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Renrenle A SWOT Analysis / TOWS Matrix

Services , Retail (Grocery)


MXC Capital SWOT Analysis / TOWS Matrix

Financial , Investment Services


Univo Pharma SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


ESTsoft SWOT Analysis / TOWS Matrix

Technology , Software & Programming


NHPC SWOT Analysis / TOWS Matrix

Utilities , Electric Utilities


Kaitori Okoku SWOT Analysis / TOWS Matrix

Services , Retail (Specialty)