Port of Tauranga (A): Changing the Rules of Engagement Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Port of Tauranga (A): Changing the Rules of Engagement case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Port of Tauranga (A): Changing the Rules of Engagement case study is a Harvard Business School (HBR) case study written by Alexander Horniman, David Cullwick. The Port of Tauranga (A): Changing the Rules of Engagement (referred as “Tauranga Port” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Leadership, Strategic planning, Strategy execution.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Port of Tauranga (A): Changing the Rules of Engagement Case Study


The Port of Tauranga, located on the north island of New Zealand, was struggling against the Port of Auckland and not doing well financially. The case depicts the bold and dramatic steps during the 1990s to change the economic circumstances. Decisions were made that changed the rules of the game and, in so doing, made Tauranga a very successful and profitable enterprise. Capital investments and a total reframing of possibilities coupled with bold management execution transformed the port to a position of world-class performance.


Case Authors : Alexander Horniman, David Cullwick

Topic : Strategy & Execution

Related Areas : Leadership, Strategic planning, Strategy execution




Calculating Net Present Value (NPV) at 6% for Port of Tauranga (A): Changing the Rules of Engagement Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10015099) -10015099 - -
Year 1 3463831 -6551268 3463831 0.9434 3267765
Year 2 3977952 -2573316 7441783 0.89 3540363
Year 3 3954239 1380923 11396022 0.8396 3320055
Year 4 3235306 4616229 14631328 0.7921 2562665
TOTAL 14631328 12690849




The Net Present Value at 6% discount rate is 2675750

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Payback Period
3. Net Present Value
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Tauranga Port have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Tauranga Port shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Port of Tauranga (A): Changing the Rules of Engagement

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Tauranga Port often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Tauranga Port needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10015099) -10015099 - -
Year 1 3463831 -6551268 3463831 0.8696 3012027
Year 2 3977952 -2573316 7441783 0.7561 3007903
Year 3 3954239 1380923 11396022 0.6575 2599976
Year 4 3235306 4616229 14631328 0.5718 1849797
TOTAL 10469703


The Net NPV after 4 years is 454604

(10469703 - 10015099 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10015099) -10015099 - -
Year 1 3463831 -6551268 3463831 0.8333 2886526
Year 2 3977952 -2573316 7441783 0.6944 2762467
Year 3 3954239 1380923 11396022 0.5787 2288333
Year 4 3235306 4616229 14631328 0.4823 1560236
TOTAL 9497562


The Net NPV after 4 years is -517537

At 20% discount rate the NPV is negative (9497562 - 10015099 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Tauranga Port to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Tauranga Port has a NPV value higher than Zero then finance managers at Tauranga Port can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Tauranga Port, then the stock price of the Tauranga Port should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Tauranga Port should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Port of Tauranga (A): Changing the Rules of Engagement

References & Further Readings

Alexander Horniman, David Cullwick (2018), "Port of Tauranga (A): Changing the Rules of Engagement Harvard Business Review Case Study. Published by HBR Publications.


Enagas SWOT Analysis / TOWS Matrix

Utilities , Natural Gas Utilities


Hebei Yangyuan ZhiHui SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Beverages (Nonalcoholic)


iFabric Corp SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


Cpl Resources SWOT Analysis / TOWS Matrix

Services , Business Services


Sunward Intel A SWOT Analysis / TOWS Matrix

Capital Goods , Constr. & Agric. Machinery


Radiant Utama SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


Intanwijaya SWOT Analysis / TOWS Matrix

Basic Materials , Chemical Manufacturing


Qiagen SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Sentinel Energy SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Equus Mining Ltd SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining