Southport Minerals, Inc. Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Southport Minerals, Inc. case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Southport Minerals, Inc. case study is a Harvard Business School (HBR) case study written by William E. Fruhan. The Southport Minerals, Inc. (referred as “Southport Minerals” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Financial management, Operations management, Project management, Risk management.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Southport Minerals, Inc. Case Study


Examines how the attractiveness of an investment project can be enhanced by making financing and operating decisions which either manage investment returns or reduce project risks.


Case Authors : William E. Fruhan

Topic : Finance & Accounting

Related Areas : Financial management, Operations management, Project management, Risk management




Calculating Net Present Value (NPV) at 6% for Southport Minerals, Inc. Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10004495) -10004495 - -
Year 1 3457279 -6547216 3457279 0.9434 3261584
Year 2 3979618 -2567598 7436897 0.89 3541846
Year 3 3949116 1381518 11386013 0.8396 3315754
Year 4 3247169 4628687 14633182 0.7921 2572062
TOTAL 14633182 12691246




The Net Present Value at 6% discount rate is 2686751

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Internal Rate of Return
3. Net Present Value
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Southport Minerals shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Southport Minerals have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Southport Minerals, Inc.

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Southport Minerals often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Southport Minerals needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10004495) -10004495 - -
Year 1 3457279 -6547216 3457279 0.8696 3006330
Year 2 3979618 -2567598 7436897 0.7561 3009163
Year 3 3949116 1381518 11386013 0.6575 2596608
Year 4 3247169 4628687 14633182 0.5718 1856579
TOTAL 10468680


The Net NPV after 4 years is 464185

(10468680 - 10004495 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10004495) -10004495 - -
Year 1 3457279 -6547216 3457279 0.8333 2881066
Year 2 3979618 -2567598 7436897 0.6944 2763624
Year 3 3949116 1381518 11386013 0.5787 2285368
Year 4 3247169 4628687 14633182 0.4823 1565957
TOTAL 9496015


The Net NPV after 4 years is -508480

At 20% discount rate the NPV is negative (9496015 - 10004495 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Southport Minerals to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Southport Minerals has a NPV value higher than Zero then finance managers at Southport Minerals can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Southport Minerals, then the stock price of the Southport Minerals should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Southport Minerals should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Southport Minerals, Inc.

References & Further Readings

William E. Fruhan (2018), "Southport Minerals, Inc. Harvard Business Review Case Study. Published by HBR Publications.


Guorui Properties SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Emclaire SWOT Analysis / TOWS Matrix

Financial , Regional Banks


AYS Ventures SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Americas Silver SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver


Corcept SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Plastrade Tech SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber


SE Power Ltd SWOT Analysis / TOWS Matrix

Utilities , Electric Utilities


Unidus SWOT Analysis / TOWS Matrix

Basic Materials , Fabricated Plastic & Rubber


LPL Financial SWOT Analysis / TOWS Matrix

Financial , Investment Services