Southwest Lumber Distributors Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Southwest Lumber Distributors case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Southwest Lumber Distributors case study is a Harvard Business School (HBR) case study written by David E. Bell, R.L. Vaughan. The Southwest Lumber Distributors (referred as “Lumber Wholesaler” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Customers, Decision making, Financial analysis, Financial markets, Pricing, Risk management.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Southwest Lumber Distributors Case Study


Concerns a lumber wholesaler who has been asked to give a forward price commitment. The market price has been volatile and the type of wood is different from that traded on the futures market. The question is: What to do about customer's request?


Case Authors : David E. Bell, R.L. Vaughan

Topic : Strategy & Execution

Related Areas : Customers, Decision making, Financial analysis, Financial markets, Pricing, Risk management




Calculating Net Present Value (NPV) at 6% for Southwest Lumber Distributors Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10019666) -10019666 - -
Year 1 3444513 -6575153 3444513 0.9434 3249541
Year 2 3958408 -2616745 7402921 0.89 3522969
Year 3 3970253 1353508 11373174 0.8396 3333501
Year 4 3223081 4576589 14596255 0.7921 2552982
TOTAL 14596255 12658993




The Net Present Value at 6% discount rate is 2639327

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Internal Rate of Return
3. Net Present Value
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Lumber Wholesaler have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Lumber Wholesaler shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Southwest Lumber Distributors

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Lumber Wholesaler often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Lumber Wholesaler needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10019666) -10019666 - -
Year 1 3444513 -6575153 3444513 0.8696 2995229
Year 2 3958408 -2616745 7402921 0.7561 2993125
Year 3 3970253 1353508 11373174 0.6575 2610506
Year 4 3223081 4576589 14596255 0.5718 1842807
TOTAL 10441667


The Net NPV after 4 years is 422001

(10441667 - 10019666 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10019666) -10019666 - -
Year 1 3444513 -6575153 3444513 0.8333 2870428
Year 2 3958408 -2616745 7402921 0.6944 2748894
Year 3 3970253 1353508 11373174 0.5787 2297600
Year 4 3223081 4576589 14596255 0.4823 1554341
TOTAL 9471263


The Net NPV after 4 years is -548403

At 20% discount rate the NPV is negative (9471263 - 10019666 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Lumber Wholesaler to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Lumber Wholesaler has a NPV value higher than Zero then finance managers at Lumber Wholesaler can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Lumber Wholesaler, then the stock price of the Lumber Wholesaler should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Lumber Wholesaler should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What can impact the cash flow of the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Southwest Lumber Distributors

References & Further Readings

David E. Bell, R.L. Vaughan (2018), "Southwest Lumber Distributors Harvard Business Review Case Study. Published by HBR Publications.


Future Architect SWOT Analysis / TOWS Matrix

Technology , Computer Networks


Mirati Ther SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


MPM SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber


Fastjet PLC SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Weizmann Forex Ltd SWOT Analysis / TOWS Matrix

Financial , Investment Services


Shreyans Industries Ltd SWOT Analysis / TOWS Matrix

Basic Materials , Paper & Paper Products


Ventus VCT PLC SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Dairy Crest SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Nissin Sugar SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


AFI Develop DRC SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Summerset Group SWOT Analysis / TOWS Matrix

Healthcare , Healthcare Facilities