Verklar Austria Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Verklar Austria case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Verklar Austria case study is a Harvard Business School (HBR) case study written by Anne Coughlan. The Verklar Austria (referred as “Verklar Quota” from here on) case study provides evaluation & decision scenario in field of Technology & Operations. It also touches upon business topics such as - Value proposition, Developing employees, Market research, Operations management.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Verklar Austria Case Study


Verklar is the leading maker of roof windows based in Europe. Its Austrian subsidiary has historically dominated the Austrian market, with about 85% market share. However, at the time of the case, its market share has dropped to about 75%, and many of its dealers have either dropped the line entirely or are buying not from the company, but from the few remaining large dealers who still buy directly from Verklar. This has prompted the president of the subsidiary to devise a new way--called the Quota System--to run the distribution channel in the country to improve performance. Asks the reader to examine the sources of market share decline and whether the proposed Quota System solves the channel's problems.


Case Authors : Anne Coughlan

Topic : Technology & Operations

Related Areas : Developing employees, Market research, Operations management




Calculating Net Present Value (NPV) at 6% for Verklar Austria Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10005149) -10005149 - -
Year 1 3447980 -6557169 3447980 0.9434 3252811
Year 2 3976684 -2580485 7424664 0.89 3539235
Year 3 3948927 1368442 11373591 0.8396 3315595
Year 4 3247215 4615657 14620806 0.7921 2572098
TOTAL 14620806 12679740




The Net Present Value at 6% discount rate is 2674591

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Profitability Index
3. Net Present Value
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Verklar Quota have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Verklar Quota shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Verklar Austria

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Technology & Operations Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Verklar Quota often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Verklar Quota needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10005149) -10005149 - -
Year 1 3447980 -6557169 3447980 0.8696 2998243
Year 2 3976684 -2580485 7424664 0.7561 3006944
Year 3 3948927 1368442 11373591 0.6575 2596484
Year 4 3247215 4615657 14620806 0.5718 1856606
TOTAL 10458277


The Net NPV after 4 years is 453128

(10458277 - 10005149 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10005149) -10005149 - -
Year 1 3447980 -6557169 3447980 0.8333 2873317
Year 2 3976684 -2580485 7424664 0.6944 2761586
Year 3 3948927 1368442 11373591 0.5787 2285259
Year 4 3247215 4615657 14620806 0.4823 1565979
TOTAL 9486141


The Net NPV after 4 years is -519008

At 20% discount rate the NPV is negative (9486141 - 10005149 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Verklar Quota to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Verklar Quota has a NPV value higher than Zero then finance managers at Verklar Quota can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Verklar Quota, then the stock price of the Verklar Quota should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Verklar Quota should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Verklar Austria

References & Further Readings

Anne Coughlan (2018), "Verklar Austria Harvard Business Review Case Study. Published by HBR Publications.


Royal Caribbean Cruises SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


Havilah Mining SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver


Create SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


OPTiM SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Nittetsu Mining SWOT Analysis / TOWS Matrix

Capital Goods , Construction - Raw Materials


Bellamys Australia Ltd SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Park24 Co Ltd SWOT Analysis / TOWS Matrix

Services , Business Services