Shouldice Hospital Ltd. (Abridged) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Shouldice Hospital Ltd. (Abridged) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Shouldice Hospital Ltd. (Abridged) case study is a Harvard Business School (HBR) case study written by Roger Hallowell, James L. Heskett. The Shouldice Hospital Ltd. (Abridged) (referred as “Hernia Shouldice” from here on) case study provides evaluation & decision scenario in field of Technology & Operations. It also touches upon business topics such as - Value proposition, Manufacturing, Organizational culture, Social enterprise.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Shouldice Hospital Ltd. (Abridged) Case Study


A hospital specializing in hernia operations is considering whether and how to expand the reach of its services.


Case Authors : Roger Hallowell, James L. Heskett

Topic : Technology & Operations

Related Areas : Manufacturing, Organizational culture, Social enterprise




Calculating Net Present Value (NPV) at 6% for Shouldice Hospital Ltd. (Abridged) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10022567) -10022567 - -
Year 1 3469823 -6552744 3469823 0.9434 3273418
Year 2 3957820 -2594924 7427643 0.89 3522446
Year 3 3970601 1375677 11398244 0.8396 3333793
Year 4 3243595 4619272 14641839 0.7921 2569231
TOTAL 14641839 12698888




The Net Present Value at 6% discount rate is 2676321

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Profitability Index
3. Payback Period
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Hernia Shouldice have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Hernia Shouldice shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Shouldice Hospital Ltd. (Abridged)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Technology & Operations Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Hernia Shouldice often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Hernia Shouldice needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10022567) -10022567 - -
Year 1 3469823 -6552744 3469823 0.8696 3017237
Year 2 3957820 -2594924 7427643 0.7561 2992681
Year 3 3970601 1375677 11398244 0.6575 2610735
Year 4 3243595 4619272 14641839 0.5718 1854536
TOTAL 10475188


The Net NPV after 4 years is 452621

(10475188 - 10022567 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10022567) -10022567 - -
Year 1 3469823 -6552744 3469823 0.8333 2891519
Year 2 3957820 -2594924 7427643 0.6944 2748486
Year 3 3970601 1375677 11398244 0.5787 2297802
Year 4 3243595 4619272 14641839 0.4823 1564234
TOTAL 9502040


The Net NPV after 4 years is -520527

At 20% discount rate the NPV is negative (9502040 - 10022567 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Hernia Shouldice to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Hernia Shouldice has a NPV value higher than Zero then finance managers at Hernia Shouldice can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Hernia Shouldice, then the stock price of the Hernia Shouldice should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Hernia Shouldice should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Shouldice Hospital Ltd. (Abridged)

References & Further Readings

Roger Hallowell, James L. Heskett (2018), "Shouldice Hospital Ltd. (Abridged) Harvard Business Review Case Study. Published by HBR Publications.


Metalyst Forgings SWOT Analysis / TOWS Matrix

Basic Materials , Misc. Fabricated Products


Moody Tech SWOT Analysis / TOWS Matrix

Consumer Cyclical , Textiles - Non Apparel


Network 18 Media SWOT Analysis / TOWS Matrix

Services , Broadcasting & Cable TV


Medtronic SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Alam Sutera Realty SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Good Vibrations Shoes SWOT Analysis / TOWS Matrix

Basic Materials , Chemical Manufacturing


Experian SWOT Analysis / TOWS Matrix

Services , Business Services


Sigmaxyz SWOT Analysis / TOWS Matrix

Services , Business Services