×




Hopital de Pontoise Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Hopital de Pontoise case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Hopital de Pontoise case study is a Harvard Business School (HBR) case study written by Richard Bohmer, Daniela Beyersdorfer, Simon Harrow. The Hopital de Pontoise (referred as “Razafindranaly Hopital” from here on) case study provides evaluation & decision scenario in field of Technology & Operations. It also touches upon business topics such as - Value proposition, Operations management.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Hopital de Pontoise Case Study


In 2010, Andre Razafindranaly, Managing Director of a large French public hospital, considers which organizational structure will help them adjust to the changing health sector environment. The move from global budget to activity-based funding has led his and many other public hospitals to suffer losses in recent years. Appointed two years previously, Razafindranaly introduced increasing financial control and encouraged organizational changes such as multidisciplinary wards differentiated by patients' lengths of stay. To what extent should he (and can he) reinforce these measures, which have increased efficiency and reduced the deficit, but also generated push-back from his doctors and staff?


Case Authors : Richard Bohmer, Daniela Beyersdorfer, Simon Harrow

Topic : Technology & Operations

Related Areas : Operations management




Calculating Net Present Value (NPV) at 6% for Hopital de Pontoise Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10029950) -10029950 - -
Year 1 3458727 -6571223 3458727 0.9434 3262950
Year 2 3965059 -2606164 7423786 0.89 3528888
Year 3 3936303 1330139 11360089 0.8396 3304996
Year 4 3233479 4563618 14593568 0.7921 2561218
TOTAL 14593568 12658053




The Net Present Value at 6% discount rate is 2628103

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Profitability Index
3. Net Present Value
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Razafindranaly Hopital have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Razafindranaly Hopital shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Hopital de Pontoise

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Technology & Operations Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Razafindranaly Hopital often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Razafindranaly Hopital needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10029950) -10029950 - -
Year 1 3458727 -6571223 3458727 0.8696 3007589
Year 2 3965059 -2606164 7423786 0.7561 2998154
Year 3 3936303 1330139 11360089 0.6575 2588183
Year 4 3233479 4563618 14593568 0.5718 1848752
TOTAL 10442678


The Net NPV after 4 years is 412728

(10442678 - 10029950 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10029950) -10029950 - -
Year 1 3458727 -6571223 3458727 0.8333 2882273
Year 2 3965059 -2606164 7423786 0.6944 2753513
Year 3 3936303 1330139 11360089 0.5787 2277953
Year 4 3233479 4563618 14593568 0.4823 1559355
TOTAL 9473094


The Net NPV after 4 years is -556856

At 20% discount rate the NPV is negative (9473094 - 10029950 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Razafindranaly Hopital to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Razafindranaly Hopital has a NPV value higher than Zero then finance managers at Razafindranaly Hopital can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Razafindranaly Hopital, then the stock price of the Razafindranaly Hopital should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Razafindranaly Hopital should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Hopital de Pontoise

References & Further Readings

Richard Bohmer, Daniela Beyersdorfer, Simon Harrow (2018), "Hopital de Pontoise Harvard Business Review Case Study. Published by HBR Publications.


Well Lead Medical SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Gz Seagull A SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Millennium Blockchain SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Motilal Oswal SWOT Analysis / TOWS Matrix

Financial , Investment Services


Qijing Machinery SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Manufacturers


Smart Metering SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


MRI Interventions SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Charter Hall Group SWOT Analysis / TOWS Matrix

Services , Real Estate Operations