Chet Huber on OnStar, Video Supplement Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Chet Huber on OnStar, Video Supplement case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Chet Huber on OnStar, Video Supplement case study is a Harvard Business School (HBR) case study written by Willy Shih. The Chet Huber on OnStar, Video Supplement (referred as “Onstar Chet” from here on) case study provides evaluation & decision scenario in field of Technology & Operations. It also touches upon business topics such as - Value proposition, Competitive strategy, Disruptive innovation, IT, Manufacturing.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Chet Huber on OnStar, Video Supplement Case Study


Chet Huber, general manager of GM's OnStar unit, givbes an update on how OnStar is doing, talks about the job OnStar does for consumers, and reflects on assembling the OnStar team. The video is organized into three chapters so that instructors may use then independently. This video is a supplement to "OnStar: Not Your Father's General Motors,: HBS Case No. 610-029.


Case Authors : Willy Shih

Topic : Technology & Operations

Related Areas : Competitive strategy, Disruptive innovation, IT, Manufacturing




Calculating Net Present Value (NPV) at 6% for Chet Huber on OnStar, Video Supplement Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10018522) -10018522 - -
Year 1 3444136 -6574386 3444136 0.9434 3249185
Year 2 3974209 -2600177 7418345 0.89 3537032
Year 3 3946928 1346751 11365273 0.8396 3313917
Year 4 3247773 4594524 14613046 0.7921 2572540
TOTAL 14613046 12672674




The Net Present Value at 6% discount rate is 2654152

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Net Present Value
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Onstar Chet have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Onstar Chet shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Chet Huber on OnStar, Video Supplement

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Technology & Operations Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Onstar Chet often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Onstar Chet needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10018522) -10018522 - -
Year 1 3444136 -6574386 3444136 0.8696 2994901
Year 2 3974209 -2600177 7418345 0.7561 3005073
Year 3 3946928 1346751 11365273 0.6575 2595169
Year 4 3247773 4594524 14613046 0.5718 1856925
TOTAL 10452068


The Net NPV after 4 years is 433546

(10452068 - 10018522 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10018522) -10018522 - -
Year 1 3444136 -6574386 3444136 0.8333 2870113
Year 2 3974209 -2600177 7418345 0.6944 2759867
Year 3 3946928 1346751 11365273 0.5787 2284102
Year 4 3247773 4594524 14613046 0.4823 1566249
TOTAL 9480331


The Net NPV after 4 years is -538191

At 20% discount rate the NPV is negative (9480331 - 10018522 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Onstar Chet to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Onstar Chet has a NPV value higher than Zero then finance managers at Onstar Chet can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Onstar Chet, then the stock price of the Onstar Chet should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Onstar Chet should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Chet Huber on OnStar, Video Supplement

References & Further Readings

Willy Shih (2018), "Chet Huber on OnStar, Video Supplement Harvard Business Review Case Study. Published by HBR Publications.


Comstock SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


BEP Intl SWOT Analysis / TOWS Matrix

Technology , Computer Hardware


American Graphite Tech SWOT Analysis / TOWS Matrix

Basic Materials , Non-Metallic Mining


Pharmaxis ADR SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Hanwhachem SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber


Quintana Energy Services SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


WhiteHawk SWOT Analysis / TOWS Matrix

Services , Business Services


Lao Feng Xiang A SWOT Analysis / TOWS Matrix

Consumer Cyclical , Jewelry & Silverware


Maeda Kosen Co Ltd SWOT Analysis / TOWS Matrix

Basic Materials , Fabricated Plastic & Rubber