Cybertech Project (A) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Cybertech Project (A) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Cybertech Project (A) case study is a Harvard Business School (HBR) case study written by David M. Upton. The Cybertech Project (A) (referred as “Exploitation Improvement” from here on) case study provides evaluation & decision scenario in field of Technology & Operations. It also touches upon business topics such as - Value proposition, Manufacturing, Marketing.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Cybertech Project (A) Case Study


Describes the development and exploitation of a radical new computer-integrated technology in the largely manual meat-processing industry. The technology has been developed by the meat industry's research organization over a period of 15 years and is now ready for commercial exploitation. Unfortunately, it is not clear how the industry can use the technology because its scale demands larger firms than currently exist and its operation requires expertise that the industry does not have. The commercializing firm is also under pressure to break the system into smaller modules, losing some of the benefits of computer integration, but gaining a dissemination path. There is another model for improvement in the industry, relying on incremental improvement, rather than radical technology change, and many have said that the project is doomed, because it might not provide the best path to improvement in the industry.


Case Authors : David M. Upton

Topic : Technology & Operations

Related Areas : Manufacturing, Marketing




Calculating Net Present Value (NPV) at 6% for Cybertech Project (A) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10010014) -10010014 - -
Year 1 3448951 -6561063 3448951 0.9434 3253727
Year 2 3972200 -2588863 7421151 0.89 3535244
Year 3 3975082 1386219 11396233 0.8396 3337555
Year 4 3242827 4629046 14639060 0.7921 2568623
TOTAL 14639060 12695149




The Net Present Value at 6% discount rate is 2685135

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Net Present Value
3. Internal Rate of Return
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Exploitation Improvement shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Exploitation Improvement have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Cybertech Project (A)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Technology & Operations Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Exploitation Improvement often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Exploitation Improvement needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10010014) -10010014 - -
Year 1 3448951 -6561063 3448951 0.8696 2999088
Year 2 3972200 -2588863 7421151 0.7561 3003554
Year 3 3975082 1386219 11396233 0.6575 2613681
Year 4 3242827 4629046 14639060 0.5718 1854097
TOTAL 10470420


The Net NPV after 4 years is 460406

(10470420 - 10010014 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10010014) -10010014 - -
Year 1 3448951 -6561063 3448951 0.8333 2874126
Year 2 3972200 -2588863 7421151 0.6944 2758472
Year 3 3975082 1386219 11396233 0.5787 2300395
Year 4 3242827 4629046 14639060 0.4823 1563863
TOTAL 9496856


The Net NPV after 4 years is -513158

At 20% discount rate the NPV is negative (9496856 - 10010014 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Exploitation Improvement to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Exploitation Improvement has a NPV value higher than Zero then finance managers at Exploitation Improvement can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Exploitation Improvement, then the stock price of the Exploitation Improvement should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Exploitation Improvement should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Cybertech Project (A)

References & Further Readings

David M. Upton (2018), "Cybertech Project (A) Harvard Business Review Case Study. Published by HBR Publications.


Hebei Sailhero Environmental SWOT Analysis / TOWS Matrix

Technology , Scientific & Technical Instr.


GrowGeneration SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Personal & Household Prods.


Nine Entertainment SWOT Analysis / TOWS Matrix

Services , Broadcasting & Cable TV


Alanco Tech Inc SWOT Analysis / TOWS Matrix

Services , Waste Management Services


Duerr AG SWOT Analysis / TOWS Matrix

Capital Goods , Constr. & Agric. Machinery


Pearl Global SWOT Analysis / TOWS Matrix

Energy , Oil & Gas Operations


Universe SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Talk Talk SWOT Analysis / TOWS Matrix

Services , Communications Services