Credit Valley Golf and Country Club Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Credit Valley Golf and Country Club case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Credit Valley Golf and Country Club case study is a Harvard Business School (HBR) case study written by Mary Heisz, Stephen Rene Frey. The Credit Valley Golf and Country Club (referred as “Golf Valley” from here on) case study provides evaluation & decision scenario in field of Technology & Operations. It also touches upon business topics such as - Value proposition, Financial analysis, Government, Operations management.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Credit Valley Golf and Country Club Case Study


Credit Valley Golf and Country Club (Credit Valley), a private golf course, would be having their annual general meeting very soon. The general manager of Credit Valley and the superintendent felt that the most pressing issue was a change to the method of irrigation being used by the golf course. This change was made necessary by newly passed government regulations. The general manager and superintendent had to prepare a proposal for the annual general meeting to convince the board of directors and the club members that a new pump house was the most viable option.


Case Authors : Mary Heisz, Stephen Rene Frey

Topic : Technology & Operations

Related Areas : Financial analysis, Government, Operations management




Calculating Net Present Value (NPV) at 6% for Credit Valley Golf and Country Club Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10009210) -10009210 - -
Year 1 3451479 -6557731 3451479 0.9434 3256112
Year 2 3966984 -2590747 7418463 0.89 3530602
Year 3 3972425 1381678 11390888 0.8396 3335325
Year 4 3234250 4615928 14625138 0.7921 2561829
TOTAL 14625138 12683867




The Net Present Value at 6% discount rate is 2674657

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Profitability Index
3. Internal Rate of Return
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Golf Valley have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Golf Valley shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Credit Valley Golf and Country Club

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Technology & Operations Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Golf Valley often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Golf Valley needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10009210) -10009210 - -
Year 1 3451479 -6557731 3451479 0.8696 3001286
Year 2 3966984 -2590747 7418463 0.7561 2999610
Year 3 3972425 1381678 11390888 0.6575 2611934
Year 4 3234250 4615928 14625138 0.5718 1849193
TOTAL 10462023


The Net NPV after 4 years is 452813

(10462023 - 10009210 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10009210) -10009210 - -
Year 1 3451479 -6557731 3451479 0.8333 2876233
Year 2 3966984 -2590747 7418463 0.6944 2754850
Year 3 3972425 1381678 11390888 0.5787 2298857
Year 4 3234250 4615928 14625138 0.4823 1559727
TOTAL 9489667


The Net NPV after 4 years is -519543

At 20% discount rate the NPV is negative (9489667 - 10009210 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Golf Valley to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Golf Valley has a NPV value higher than Zero then finance managers at Golf Valley can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Golf Valley, then the stock price of the Golf Valley should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Golf Valley should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What can impact the cash flow of the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Credit Valley Golf and Country Club

References & Further Readings

Mary Heisz, Stephen Rene Frey (2018), "Credit Valley Golf and Country Club Harvard Business Review Case Study. Published by HBR Publications.


AvalonBay SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Beghelli SWOT Analysis / TOWS Matrix

Consumer Cyclical , Furniture & Fixtures


Blucora SWOT Analysis / TOWS Matrix

Technology , Computer Services


Interfor Corp SWOT Analysis / TOWS Matrix

Basic Materials , Forestry & Wood Products


Fanhua SWOT Analysis / TOWS Matrix

Financial , Insurance (Miscellaneous)


Nikko Co Ltd SWOT Analysis / TOWS Matrix

Capital Goods , Constr. & Agric. Machinery


K Wah Int SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Berjaya Land SWOT Analysis / TOWS Matrix

Services , Casinos & Gaming


WCE Holdings SWOT Analysis / TOWS Matrix

Transportation , Misc. Transportation