Fiona and Frederic Bonner Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Fiona and Frederic Bonner case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Fiona and Frederic Bonner case study is a Harvard Business School (HBR) case study written by Jennifer Petriglieri, Gianpiero Petriglieri, Otilia Obodaru. The Fiona and Frederic Bonner (referred as “Bonner Frederic” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Work-life balance.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Fiona and Frederic Bonner Case Study


Frederic and Fiona Bonner follows the relationship and careers of an investment banker and a tech entrepreneur as their personal and professional lives unfold. It hinges on the dilemma they face ten years into their marriage and with two young children, as job opportunities pull them to different sides of the United States. The case invites students to explore their opinions about FrA?dA?ric and Fiona's life and careers to date, their successes, failures and trade-offs, and their options going forward. By doing so it creates a space for students to reflect on and discuss their experiences and expectations of "managing" the interplay between work, love, and family in their lives. The case challenges students to examine how they define success professionally and personally; how, with, and for whom they make major decisions; whether they can "have it all" and what that might look like.


Case Authors : Jennifer Petriglieri, Gianpiero Petriglieri, Otilia Obodaru

Topic : Leadership & Managing People

Related Areas : Work-life balance




Calculating Net Present Value (NPV) at 6% for Fiona and Frederic Bonner Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10001266) -10001266 - -
Year 1 3446544 -6554722 3446544 0.9434 3251457
Year 2 3966166 -2588556 7412710 0.89 3529874
Year 3 3975439 1386883 11388149 0.8396 3337855
Year 4 3237755 4624638 14625904 0.7921 2564605
TOTAL 14625904 12683791




The Net Present Value at 6% discount rate is 2682525

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Internal Rate of Return
3. Payback Period
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Bonner Frederic have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Bonner Frederic shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Fiona and Frederic Bonner

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Bonner Frederic often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Bonner Frederic needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10001266) -10001266 - -
Year 1 3446544 -6554722 3446544 0.8696 2996995
Year 2 3966166 -2588556 7412710 0.7561 2998991
Year 3 3975439 1386883 11388149 0.6575 2613916
Year 4 3237755 4624638 14625904 0.5718 1851197
TOTAL 10461099


The Net NPV after 4 years is 459833

(10461099 - 10001266 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10001266) -10001266 - -
Year 1 3446544 -6554722 3446544 0.8333 2872120
Year 2 3966166 -2588556 7412710 0.6944 2754282
Year 3 3975439 1386883 11388149 0.5787 2300601
Year 4 3237755 4624638 14625904 0.4823 1561417
TOTAL 9488421


The Net NPV after 4 years is -512845

At 20% discount rate the NPV is negative (9488421 - 10001266 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Bonner Frederic to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Bonner Frederic has a NPV value higher than Zero then finance managers at Bonner Frederic can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Bonner Frederic, then the stock price of the Bonner Frederic should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Bonner Frederic should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Fiona and Frederic Bonner

References & Further Readings

Jennifer Petriglieri, Gianpiero Petriglieri, Otilia Obodaru (2018), "Fiona and Frederic Bonner Harvard Business Review Case Study. Published by HBR Publications.


Nissan SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Ebro Foods SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Sanrio Co Ltd SWOT Analysis / TOWS Matrix

Services , Retail (Specialty)


M B T SWOT Analysis / TOWS Matrix

Financial , Regional Banks


Kuk Young G M SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Hioki EE Corp SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


XPS Pensions SWOT Analysis / TOWS Matrix

Financial , Investment Services


Diamondback SWOT Analysis / TOWS Matrix

Energy , Oil & Gas Operations


Skeena Resources SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver