×




Venture Capital Vignettes: Difficult Financings Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Venture Capital Vignettes: Difficult Financings case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Venture Capital Vignettes: Difficult Financings case study is a Harvard Business School (HBR) case study written by G. Felda Hardymon, Ann Leamon. The Venture Capital Vignettes: Difficult Financings (referred as “Financings Vignettes” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Decision making, Strategy, Venture capital.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Venture Capital Vignettes: Difficult Financings Case Study


These three short vignettes depict investment professionals considering difficult financings for companies in their portfolios. For one reason or another, each company has under-performed expectations. Should the protagonist recommend that the firm participate or not, or should he try to revise it? Can the firm exercise any influence, and are the potential gains worth the time and effort that will be required?


Case Authors : G. Felda Hardymon, Ann Leamon

Topic : Finance & Accounting

Related Areas : Decision making, Strategy, Venture capital




Calculating Net Present Value (NPV) at 6% for Venture Capital Vignettes: Difficult Financings Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10007557) -10007557 - -
Year 1 3449233 -6558324 3449233 0.9434 3253993
Year 2 3954898 -2603426 7404131 0.89 3519845
Year 3 3960576 1357150 11364707 0.8396 3325376
Year 4 3246692 4603842 14611399 0.7921 2571684
TOTAL 14611399 12670899




The Net Present Value at 6% discount rate is 2663342

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Payback Period
3. Internal Rate of Return
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Financings Vignettes have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Financings Vignettes shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Venture Capital Vignettes: Difficult Financings

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Financings Vignettes often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Financings Vignettes needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10007557) -10007557 - -
Year 1 3449233 -6558324 3449233 0.8696 2999333
Year 2 3954898 -2603426 7404131 0.7561 2990471
Year 3 3960576 1357150 11364707 0.6575 2604143
Year 4 3246692 4603842 14611399 0.5718 1856307
TOTAL 10450254


The Net NPV after 4 years is 442697

(10450254 - 10007557 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10007557) -10007557 - -
Year 1 3449233 -6558324 3449233 0.8333 2874361
Year 2 3954898 -2603426 7404131 0.6944 2746457
Year 3 3960576 1357150 11364707 0.5787 2292000
Year 4 3246692 4603842 14611399 0.4823 1565727
TOTAL 9478545


The Net NPV after 4 years is -529012

At 20% discount rate the NPV is negative (9478545 - 10007557 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Financings Vignettes to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Financings Vignettes has a NPV value higher than Zero then finance managers at Financings Vignettes can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Financings Vignettes, then the stock price of the Financings Vignettes should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Financings Vignettes should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Venture Capital Vignettes: Difficult Financings

References & Further Readings

G. Felda Hardymon, Ann Leamon (2018), "Venture Capital Vignettes: Difficult Financings Harvard Business Review Case Study. Published by HBR Publications.


PerkinElmer SWOT Analysis / TOWS Matrix

Technology , Scientific & Technical Instr.


FC Global SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Tomson SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Jetpay Corp SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services


Rivera SWOT Analysis / TOWS Matrix

Financial , Investment Services


Gray Television A SWOT Analysis / TOWS Matrix

Services , Broadcasting & Cable TV


Sata Construction SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Taikisha Ltd SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services