×




Fremont Financial Corp. Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Fremont Financial Corp. case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Fremont Financial Corp. case study is a Harvard Business School (HBR) case study written by Erik Sirri, Ann Zeitung. The Fremont Financial Corp. (referred as “Fremont Loan” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, .

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Fremont Financial Corp. Case Study


Fremont Financial is an asset-based lender to middle-market companies. The firm has three options to raise capital to finance its loan portfolio. Fremont can (1) extend its existing bank line of credit, (2) issue commercial paper through a special purpose-conduit, or (3) securitize and sell the loan portfolio into the capital markets. The case emphasizes the problems and potential solutions to asymmetric information and moral hazard problems that are endemic to financial intermediation.


Case Authors : Erik Sirri, Ann Zeitung

Topic : Finance & Accounting

Related Areas :




Calculating Net Present Value (NPV) at 6% for Fremont Financial Corp. Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10000600) -10000600 - -
Year 1 3456164 -6544436 3456164 0.9434 3260532
Year 2 3960134 -2584302 7416298 0.89 3524505
Year 3 3959901 1375599 11376199 0.8396 3324809
Year 4 3231490 4607089 14607689 0.7921 2559643
TOTAL 14607689 12669489




The Net Present Value at 6% discount rate is 2668889

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Payback Period
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Fremont Loan shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Fremont Loan have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Fremont Financial Corp.

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Fremont Loan often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Fremont Loan needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10000600) -10000600 - -
Year 1 3456164 -6544436 3456164 0.8696 3005360
Year 2 3960134 -2584302 7416298 0.7561 2994430
Year 3 3959901 1375599 11376199 0.6575 2603699
Year 4 3231490 4607089 14607689 0.5718 1847615
TOTAL 10451104


The Net NPV after 4 years is 450504

(10451104 - 10000600 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10000600) -10000600 - -
Year 1 3456164 -6544436 3456164 0.8333 2880137
Year 2 3960134 -2584302 7416298 0.6944 2750093
Year 3 3959901 1375599 11376199 0.5787 2291609
Year 4 3231490 4607089 14607689 0.4823 1558396
TOTAL 9480235


The Net NPV after 4 years is -520365

At 20% discount rate the NPV is negative (9480235 - 10000600 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Fremont Loan to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Fremont Loan has a NPV value higher than Zero then finance managers at Fremont Loan can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Fremont Loan, then the stock price of the Fremont Loan should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Fremont Loan should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Fremont Financial Corp.

References & Further Readings

Erik Sirri, Ann Zeitung (2018), "Fremont Financial Corp. Harvard Business Review Case Study. Published by HBR Publications.


iSelect SWOT Analysis / TOWS Matrix

Technology , Computer Services


Guangxia A SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Beverages (Alcoholic)


Objective Corp Ltd SWOT Analysis / TOWS Matrix

Technology , Software & Programming


PB Bancorp SWOT Analysis / TOWS Matrix

Financial , Regional Banks


Atlas Copco A SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


Lapidoth SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


Blackmores SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


China Jushi SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Personal & Household Prods.


Roche Bobois SWOT Analysis / TOWS Matrix

Consumer Cyclical , Furniture & Fixtures


Kafrit SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber