×




Back to School: Real Estate Development of Off-Campus Student Housing Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Back to School: Real Estate Development of Off-Campus Student Housing case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Back to School: Real Estate Development of Off-Campus Student Housing case study is a Harvard Business School (HBR) case study written by Craig Furfine. The Back to School: Real Estate Development of Off-Campus Student Housing (referred as “Lenard Housing” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, .

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Back to School: Real Estate Development of Off-Campus Student Housing Case Study


Christopher Lenard and his longtime friend Kimberly Slater are exploring the idea of developing a student-housing complex near the University of Wisconsin, Madison, by replicating Slater's highly successful, similar development near the University of Florida. Madison seemed to present attractive market and demographic conditions for investment in student housing in the summer of 2012. But before committing a large share of his personal wealth to the project, Lenard needs to conduct a more careful analysis of its potential risks and returns. By putting themselves into the shoes of a budding real estate entrepreneur, students will evaluate both the merits and pitfalls of various approaches to the financial analysis of real estate development projects.


Case Authors : Craig Furfine

Topic : Finance & Accounting

Related Areas :




Calculating Net Present Value (NPV) at 6% for Back to School: Real Estate Development of Off-Campus Student Housing Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10022958) -10022958 - -
Year 1 3456852 -6566106 3456852 0.9434 3261181
Year 2 3966778 -2599328 7423630 0.89 3530418
Year 3 3954380 1355052 11378010 0.8396 3320174
Year 4 3249065 4604117 14627075 0.7921 2573564
TOTAL 14627075 12685337




The Net Present Value at 6% discount rate is 2662379

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Payback Period
3. Profitability Index
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Lenard Housing have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Lenard Housing shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Back to School: Real Estate Development of Off-Campus Student Housing

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Lenard Housing often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Lenard Housing needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10022958) -10022958 - -
Year 1 3456852 -6566106 3456852 0.8696 3005958
Year 2 3966778 -2599328 7423630 0.7561 2999454
Year 3 3954380 1355052 11378010 0.6575 2600069
Year 4 3249065 4604117 14627075 0.5718 1857663
TOTAL 10463145


The Net NPV after 4 years is 440187

(10463145 - 10022958 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10022958) -10022958 - -
Year 1 3456852 -6566106 3456852 0.8333 2880710
Year 2 3966778 -2599328 7423630 0.6944 2754707
Year 3 3954380 1355052 11378010 0.5787 2288414
Year 4 3249065 4604117 14627075 0.4823 1566872
TOTAL 9490703


The Net NPV after 4 years is -532255

At 20% discount rate the NPV is negative (9490703 - 10022958 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Lenard Housing to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Lenard Housing has a NPV value higher than Zero then finance managers at Lenard Housing can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Lenard Housing, then the stock price of the Lenard Housing should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Lenard Housing should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Back to School: Real Estate Development of Off-Campus Student Housing

References & Further Readings

Craig Furfine (2018), "Back to School: Real Estate Development of Off-Campus Student Housing Harvard Business Review Case Study. Published by HBR Publications.


Nameson SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


Charah Solutions SWOT Analysis / TOWS Matrix

Utilities , Electric Utilities


Starlite SWOT Analysis / TOWS Matrix

Basic Materials , Containers & Packaging


Ophir SWOT Analysis / TOWS Matrix

Energy , Oil & Gas - Integrated


Low & Bonar SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Singamas Container SWOT Analysis / TOWS Matrix

Basic Materials , Containers & Packaging


Remsons Industries Ltd SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Parts