Rwandan Tea Industry: Looking into the Future Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Rwandan Tea Industry: Looking into the Future case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Rwandan Tea Industry: Looking into the Future case study is a Harvard Business School (HBR) case study written by Cate Reavis, Debora L. Spar. The Rwandan Tea Industry: Looking into the Future (referred as “Tea Rwandan” from here on) case study provides evaluation & decision scenario in field of Global Business. It also touches upon business topics such as - Value proposition, Emerging markets, Government.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Rwandan Tea Industry: Looking into the Future Case Study


In 2003, the Rwandan government was focused on transforming the nation's tea industry into a world-class competitor. To accomplish this objective and stave off the downward prices that plagued the international tea market, the government believed that the industry needed to develop a diversified and value-added product portfolio. This would entail large investments in improving quality and productivity, as well as a new and more competitive price scheme for farmers. Part of the government's strategy for the tea industry involved wide-scale privatization to infuse the industry with capital, competition, and management expertise. But it remained uncertain whether the government could achieve its own objectives while ceding control to private, probably foreign, owners. Could Rwandan tea find its way in a complicated and highly competitive international market?


Case Authors : Cate Reavis, Debora L. Spar

Topic : Global Business

Related Areas : Emerging markets, Government




Calculating Net Present Value (NPV) at 6% for Rwandan Tea Industry: Looking into the Future Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10006922) -10006922 - -
Year 1 3447880 -6559042 3447880 0.9434 3252717
Year 2 3972230 -2586812 7420110 0.89 3535271
Year 3 3949070 1362258 11369180 0.8396 3315715
Year 4 3244293 4606551 14613473 0.7921 2569784
TOTAL 14613473 12673487




The Net Present Value at 6% discount rate is 2666565

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Payback Period
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Tea Rwandan have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Tea Rwandan shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Rwandan Tea Industry: Looking into the Future

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Global Business Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Tea Rwandan often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Tea Rwandan needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10006922) -10006922 - -
Year 1 3447880 -6559042 3447880 0.8696 2998157
Year 2 3972230 -2586812 7420110 0.7561 3003577
Year 3 3949070 1362258 11369180 0.6575 2596578
Year 4 3244293 4606551 14613473 0.5718 1854935
TOTAL 10453246


The Net NPV after 4 years is 446324

(10453246 - 10006922 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10006922) -10006922 - -
Year 1 3447880 -6559042 3447880 0.8333 2873233
Year 2 3972230 -2586812 7420110 0.6944 2758493
Year 3 3949070 1362258 11369180 0.5787 2285341
Year 4 3244293 4606551 14613473 0.4823 1564570
TOTAL 9481638


The Net NPV after 4 years is -525284

At 20% discount rate the NPV is negative (9481638 - 10006922 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Tea Rwandan to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Tea Rwandan has a NPV value higher than Zero then finance managers at Tea Rwandan can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Tea Rwandan, then the stock price of the Tea Rwandan should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Tea Rwandan should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Rwandan Tea Industry: Looking into the Future

References & Further Readings

Cate Reavis, Debora L. Spar (2018), "Rwandan Tea Industry: Looking into the Future Harvard Business Review Case Study. Published by HBR Publications.


Chongqing Zaisheng Tech SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Personal & Household Prods.


Angling Direct SWOT Analysis / TOWS Matrix

Technology , Computer Services


Gear Energy SWOT Analysis / TOWS Matrix

Energy , Oil & Gas Operations


Mcig Inc SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Tobacco


Perisai Petroleum SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


Silkroad Nickel SWOT Analysis / TOWS Matrix

Basic Materials , Misc. Fabricated Products


Drax Group SWOT Analysis / TOWS Matrix

Utilities , Electric Utilities


Atlantica Yield SWOT Analysis / TOWS Matrix

Utilities , Electric Utilities


INDS ROMI ON SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods