×




The Critical Role of Timing in Managing Intellectual Property Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for The Critical Role of Timing in Managing Intellectual Property case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. The Critical Role of Timing in Managing Intellectual Property case study is a Harvard Business School (HBR) case study written by Timothy A Lemper. The The Critical Role of Timing in Managing Intellectual Property (referred as “Intellectual Property” from here on) case study provides evaluation & decision scenario in field of Global Business. It also touches upon business topics such as - Value proposition, International business.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of The Critical Role of Timing in Managing Intellectual Property Case Study


In today's environment, timing is a critical part of business strategy. Nowhere is this truer than as regards managing intellectual property in an increasingly global marketplace. The creation and protection of intellectual property assets often depends on consistently taking the right legal action at the right time. The consequences of failing to do so can be disastrous but may only be felt at a later time or in other markets. The difficulty for business people lies in the fact that the time-sensitive aspects of intellectual property cannot be managed effectively by relying on intuition or resolving to see a lawyer when the need arises. This article provides a basic primer on the critical role of timing in identifying, creating, and protecting intellectual property assets. It discusses the most common types of intellectual property-patents, copyrights, trademarks, and trade secrets-and compares the role of timing in the creation and protection of each asset type. Most importantly, it summarizes the key issues of timing in the creation and protection of intellectual property.


Case Authors : Timothy A Lemper

Topic : Global Business

Related Areas : International business




Calculating Net Present Value (NPV) at 6% for The Critical Role of Timing in Managing Intellectual Property Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10020377) -10020377 - -
Year 1 3467627 -6552750 3467627 0.9434 3271346
Year 2 3970509 -2582241 7438136 0.89 3533739
Year 3 3953311 1371070 11391447 0.8396 3319276
Year 4 3238566 4609636 14630013 0.7921 2565248
TOTAL 14630013 12689609




The Net Present Value at 6% discount rate is 2669232

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Payback Period
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Intellectual Property have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Intellectual Property shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of The Critical Role of Timing in Managing Intellectual Property

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Global Business Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Intellectual Property often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Intellectual Property needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10020377) -10020377 - -
Year 1 3467627 -6552750 3467627 0.8696 3015328
Year 2 3970509 -2582241 7438136 0.7561 3002275
Year 3 3953311 1371070 11391447 0.6575 2599366
Year 4 3238566 4609636 14630013 0.5718 1851661
TOTAL 10468630


The Net NPV after 4 years is 448253

(10468630 - 10020377 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10020377) -10020377 - -
Year 1 3467627 -6552750 3467627 0.8333 2889689
Year 2 3970509 -2582241 7438136 0.6944 2757298
Year 3 3953311 1371070 11391447 0.5787 2287796
Year 4 3238566 4609636 14630013 0.4823 1561808
TOTAL 9496591


The Net NPV after 4 years is -523786

At 20% discount rate the NPV is negative (9496591 - 10020377 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Intellectual Property to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Intellectual Property has a NPV value higher than Zero then finance managers at Intellectual Property can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Intellectual Property, then the stock price of the Intellectual Property should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Intellectual Property should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of The Critical Role of Timing in Managing Intellectual Property

References & Further Readings

Timothy A Lemper (2018), "The Critical Role of Timing in Managing Intellectual Property Harvard Business Review Case Study. Published by HBR Publications.


Roma SWOT Analysis / TOWS Matrix

Services , Recreational Activities


MYnd Analytics SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Over Wire Holdings Ltd SWOT Analysis / TOWS Matrix

Services , Communications Services


Star Bulk Carriers SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


American Graphite Tech SWOT Analysis / TOWS Matrix

Basic Materials , Non-Metallic Mining


Cardinal SWOT Analysis / TOWS Matrix

Basic Materials , Paper & Paper Products


LEAP SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Carnival ADS SWOT Analysis / TOWS Matrix

Services , Recreational Activities


Silver Life SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Acusphere Inc SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs