Replacing Hong Kong's ID Card (A): Fighting Identity Theft Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Replacing Hong Kong's ID Card (A): Fighting Identity Theft case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Replacing Hong Kong's ID Card (A): Fighting Identity Theft case study is a Harvard Business School (HBR) case study written by Ali F. Farhoomand, Francois Roy. The Replacing Hong Kong's ID Card (A): Fighting Identity Theft (referred as “Id Card” from here on) case study provides evaluation & decision scenario in field of Global Business. It also touches upon business topics such as - Value proposition, .

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Replacing Hong Kong's ID Card (A): Fighting Identity Theft Case Study


Discusses the plans of the Hong Kong government to seek approval of its proposal to replace the current Hong Kong ID card with a smart ID card. The approval in question is sought from the Hong Kong legislature. Introduces students to the reason behind the current ID card replacement in Hong Kong: the vulnerability of the current card to counterfeiting and the increased risk of identity theft in Hong Kong. Identity theft is a growing problem around the world and the fastest growing crime in the United States. Students are asked to suggest a list of criteria for Hong Kong's new ID card.


Case Authors : Ali F. Farhoomand, Francois Roy

Topic : Global Business

Related Areas :




Calculating Net Present Value (NPV) at 6% for Replacing Hong Kong's ID Card (A): Fighting Identity Theft Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10017991) -10017991 - -
Year 1 3444957 -6573034 3444957 0.9434 3249959
Year 2 3975467 -2597567 7420424 0.89 3538151
Year 3 3938436 1340869 11358860 0.8396 3306787
Year 4 3247781 4588650 14606641 0.7921 2572547
TOTAL 14606641 12667444




The Net Present Value at 6% discount rate is 2649453

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Internal Rate of Return
3. Payback Period
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Id Card have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Id Card shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Replacing Hong Kong's ID Card (A): Fighting Identity Theft

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Global Business Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Id Card often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Id Card needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10017991) -10017991 - -
Year 1 3444957 -6573034 3444957 0.8696 2995615
Year 2 3975467 -2597567 7420424 0.7561 3006024
Year 3 3938436 1340869 11358860 0.6575 2589586
Year 4 3247781 4588650 14606641 0.5718 1856929
TOTAL 10448154


The Net NPV after 4 years is 430163

(10448154 - 10017991 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10017991) -10017991 - -
Year 1 3444957 -6573034 3444957 0.8333 2870798
Year 2 3975467 -2597567 7420424 0.6944 2760741
Year 3 3938436 1340869 11358860 0.5787 2279188
Year 4 3247781 4588650 14606641 0.4823 1566252
TOTAL 9476978


The Net NPV after 4 years is -541013

At 20% discount rate the NPV is negative (9476978 - 10017991 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Id Card to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Id Card has a NPV value higher than Zero then finance managers at Id Card can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Id Card, then the stock price of the Id Card should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Id Card should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Replacing Hong Kong's ID Card (A): Fighting Identity Theft

References & Further Readings

Ali F. Farhoomand, Francois Roy (2018), "Replacing Hong Kong's ID Card (A): Fighting Identity Theft Harvard Business Review Case Study. Published by HBR Publications.


Emerald Health SWOT Analysis / TOWS Matrix

Energy , Oil & Gas Operations


Flexiintl Sftware Inc SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Seabridge Gold SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver


Idc Fluidcontrol A SWOT Analysis / TOWS Matrix

Basic Materials , Misc. Fabricated Products


Hisaka Works Ltd SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


North Hauler Joint SWOT Analysis / TOWS Matrix

Capital Goods , Constr. & Agric. Machinery


Kodensha SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


FIH Group SWOT Analysis / TOWS Matrix

Services , Retail (Department & Discount)