Brazil: Leading the BRICs? Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Brazil: Leading the BRICs? case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Brazil: Leading the BRICs? case study is a Harvard Business School (HBR) case study written by Arthur A. Daemmrich, Aldo Musacchio. The Brazil: Leading the BRICs? (referred as “Rousseff Brazil” from here on) case study provides evaluation & decision scenario in field of Global Business. It also touches upon business topics such as - Value proposition, Policy.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Brazil: Leading the BRICs? Case Study


Brazil's new president, Dilma Rousseff, had announced plans to sustain GDP growth above 5 percent annually and continue the country's leadership role among emerging economies. Between 2003 and 2010, Brazil benefited from strong economic growth and stable policies under the Lula administration. Brazil also increasingly led the BRICs (the fast-growing countries of Brazil, Russia, India, and China) in multilateral negotiations, notably in the World Trade Organization's Doha Round. Yet Brazil's actions to enforce a compulsory license of a patented therapy for HIV/AIDS and its victory in a longstanding WTO dispute with the United States over cotton subsidies had created tensions with major trading partners. Entering office in January 2011, Rousseff had the opportunity to outline a new agenda for international trade. Specifically, she had to decide whether to seek completion of the Doha Round, which was in a stalemate due to disputes over global intellectual property rules and agricultural subsidies and tariffs, or to instead pursue regional trade agreements in South and Central America. Rousseff also pledged active government involvement in the economy, described in the case as "Brazilian capitalism," but it was unclear whether fiscal expansion coupled with conservative monetary policies would reduce bottlenecks to growth and further temper Brazil's high inequality.


Case Authors : Arthur A. Daemmrich, Aldo Musacchio

Topic : Global Business

Related Areas : Policy




Calculating Net Present Value (NPV) at 6% for Brazil: Leading the BRICs? Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10013249) -10013249 - -
Year 1 3468550 -6544699 3468550 0.9434 3272217
Year 2 3959129 -2585570 7427679 0.89 3523611
Year 3 3970997 1385427 11398676 0.8396 3334126
Year 4 3225030 4610457 14623706 0.7921 2554526
TOTAL 14623706 12684479




The Net Present Value at 6% discount rate is 2671230

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Payback Period
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Rousseff Brazil shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Rousseff Brazil have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Brazil: Leading the BRICs?

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Global Business Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Rousseff Brazil often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Rousseff Brazil needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10013249) -10013249 - -
Year 1 3468550 -6544699 3468550 0.8696 3016130
Year 2 3959129 -2585570 7427679 0.7561 2993670
Year 3 3970997 1385427 11398676 0.6575 2610995
Year 4 3225030 4610457 14623706 0.5718 1843921
TOTAL 10464717


The Net NPV after 4 years is 451468

(10464717 - 10013249 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10013249) -10013249 - -
Year 1 3468550 -6544699 3468550 0.8333 2890458
Year 2 3959129 -2585570 7427679 0.6944 2749395
Year 3 3970997 1385427 11398676 0.5787 2298031
Year 4 3225030 4610457 14623706 0.4823 1555281
TOTAL 9493165


The Net NPV after 4 years is -520084

At 20% discount rate the NPV is negative (9493165 - 10013249 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Rousseff Brazil to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Rousseff Brazil has a NPV value higher than Zero then finance managers at Rousseff Brazil can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Rousseff Brazil, then the stock price of the Rousseff Brazil should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Rousseff Brazil should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Brazil: Leading the BRICs?

References & Further Readings

Arthur A. Daemmrich, Aldo Musacchio (2018), "Brazil: Leading the BRICs? Harvard Business Review Case Study. Published by HBR Publications.


ERBA Diagnostics SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Dawonsys SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Shandong Hi-speed SWOT Analysis / TOWS Matrix

Transportation , Misc. Transportation


Awox SWOT Analysis / TOWS Matrix

Consumer Cyclical , Audio & Video Equipment


Galapagos SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


China Film SWOT Analysis / TOWS Matrix

Services , Motion Pictures


Zhongtai Chem A SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber


Fidelity Financial SWOT Analysis / TOWS Matrix

Financial , Insurance (Prop. & Casualty)


Jiangyin Electrical Alloy SWOT Analysis / TOWS Matrix

Basic Materials , Misc. Fabricated Products