Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?
At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. First Energy case study is a Harvard Business School (HBR) case study written by Chandra Sekhar Ramasastry, Niraj Dawar. The First Energy (referred as “Household Lpg” from here on) case study provides evaluation & decision scenario in field of Innovation & Entrepreneurship. It also touches upon business topics such as - Value proposition, International business, Marketing, Sustainability.
The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.
In September 2011, the CEO of First Energy Private Ltd, a startup enterprise in the alternative energy industry in India, is facing a flashpoint. The company has commercialized the technology of biomass cooking stoves and has been providing, since 2007, clean and affordable cooking solutions to customers in rural India. A marginal hike in price of biomass fuel in early 2011 has, however, led to a steep fall in demand making the continuance in the rural household market unsustainable. The company does not have a level playing field in the household segment because the competitor product, liquid petroleum gas (LPG), enjoys price subsidy provided by the federal government. First Energy has been quick to find its bearings by targeting a niche market in the urban commercial market consisting of restaurants, eateries and hostels. While the margins are high in this segment, the volumes are low. The company must therefore build scale to be able to service the investments in plant capacity, which is being under-utilized. The case enables students to come up with strategies for market expansion for the CEO. They will also take a call on whether to exit from or hold on to the household segment where the margins are low but the volumes, in the light of the imminent de-subsidization of LPG, would be high.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 6 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10002820) | -10002820 | - | - | |
Year 1 | 3466657 | -6536163 | 3466657 | 0.9434 | 3270431 |
Year 2 | 3982281 | -2553882 | 7448938 | 0.89 | 3544216 |
Year 3 | 3936833 | 1382951 | 11385771 | 0.8396 | 3305441 |
Year 4 | 3231811 | 4614762 | 14617582 | 0.7921 | 2559897 |
TOTAL | 14617582 | 12679985 |
In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -
Capital Budgeting Approaches
There are four types of capital budgeting techniques that are widely used in the corporate world –
1. Net Present Value
2. Profitability Index
3. Internal Rate of Return
4. Payback Period
Apart from the Payback period method which is an additive method, rest of the methods are based on
Discounted Cash Flow
technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.
Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –
1. Timing of the expected cash flows – stockholders of Household Lpg have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Household Lpg shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0
Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate.
Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.
Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project
In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Household Lpg often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.
To overcome such scenarios managers at Household Lpg needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.
After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 15 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10002820) | -10002820 | - | - | |
Year 1 | 3466657 | -6536163 | 3466657 | 0.8696 | 3014484 |
Year 2 | 3982281 | -2553882 | 7448938 | 0.7561 | 3011177 |
Year 3 | 3936833 | 1382951 | 11385771 | 0.6575 | 2588532 |
Year 4 | 3231811 | 4614762 | 14617582 | 0.5718 | 1847798 |
TOTAL | 10461991 |
(10461991 - 10002820 )
If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 20 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10002820) | -10002820 | - | - | |
Year 1 | 3466657 | -6536163 | 3466657 | 0.8333 | 2888881 |
Year 2 | 3982281 | -2553882 | 7448938 | 0.6944 | 2765473 |
Year 3 | 3936833 | 1382951 | 11385771 | 0.5787 | 2278260 |
Year 4 | 3231811 | 4614762 | 14617582 | 0.4823 | 1558551 |
TOTAL | 9491164 |
At 20% discount rate the NPV is negative (9491164 - 10002820 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Household Lpg to discount cash flow at lower discount rates such as 15%.
Simplest Approach – If the investment project of Household Lpg has a NPV value higher than Zero then finance managers at Household Lpg can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.
In theory if the required rate of return or discount rate is chosen correctly by finance managers at Household Lpg, then the stock price of the Household Lpg should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.
In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.
Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Household Lpg should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –
Understanding of risks involved in the project.
What can impact the cash flow of the project.
What will be a multi year spillover effect of various taxation regulations.
What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.
What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.
Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.
Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.
Chandra Sekhar Ramasastry, Niraj Dawar (2018), "First Energy Harvard Business Review Case Study. Published by HBR Publications.
Feel free to connect with us if you need business research.
You can download Excel Template of Case Study Solution & Analysis of First Energy
Services , Restaurants
Utilities , Electric Utilities
Services , Communications Services
Consumer Cyclical , Furniture & Fixtures
Basic Materials , Chemicals - Plastics & Rubber
Services , Restaurants
Energy , Coal
Consumer Cyclical , Tires
Financial , Regional Banks
Capital Goods , Constr. - Supplies & Fixtures
Services , Business Services