Proteus Biomedical: Making Pigs Fly Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Proteus Biomedical: Making Pigs Fly case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Proteus Biomedical: Making Pigs Fly case study is a Harvard Business School (HBR) case study written by Richard G. Hamermesh, Lauren Barley, Ginger L. Graham. The Proteus Biomedical: Making Pigs Fly (referred as “Color.proteus Proteus” from here on) case study provides evaluation & decision scenario in field of Innovation & Entrepreneurship. It also touches upon business topics such as - Value proposition, Intellectual property, Negotiations, Organizational structure, Strategy.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Proteus Biomedical: Making Pigs Fly Case Study


To maximize their effectiveness, color cases should be printed in color.Proteus is a healthcare start-up that has developed technology to embed electronics for computing and sensing in existing medical devices and drugs. The technology could potentially change the basis of competition in the pharmaceutical industry. The company is currently considering a number of licensing and business development deals and must choose which one(s) to pursue.


Case Authors : Richard G. Hamermesh, Lauren Barley, Ginger L. Graham

Topic : Innovation & Entrepreneurship

Related Areas : Intellectual property, Negotiations, Organizational structure, Strategy




Calculating Net Present Value (NPV) at 6% for Proteus Biomedical: Making Pigs Fly Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10012756) -10012756 - -
Year 1 3455604 -6557152 3455604 0.9434 3260004
Year 2 3953616 -2603536 7409220 0.89 3518704
Year 3 3974205 1370669 11383425 0.8396 3336819
Year 4 3224251 4594920 14607676 0.7921 2553909
TOTAL 14607676 12669436




The Net Present Value at 6% discount rate is 2656680

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Profitability Index
3. Net Present Value
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Color.proteus Proteus shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Color.proteus Proteus have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Proteus Biomedical: Making Pigs Fly

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Innovation & Entrepreneurship Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Color.proteus Proteus often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Color.proteus Proteus needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10012756) -10012756 - -
Year 1 3455604 -6557152 3455604 0.8696 3004873
Year 2 3953616 -2603536 7409220 0.7561 2989502
Year 3 3974205 1370669 11383425 0.6575 2613104
Year 4 3224251 4594920 14607676 0.5718 1843476
TOTAL 10450955


The Net NPV after 4 years is 438199

(10450955 - 10012756 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10012756) -10012756 - -
Year 1 3455604 -6557152 3455604 0.8333 2879670
Year 2 3953616 -2603536 7409220 0.6944 2745567
Year 3 3974205 1370669 11383425 0.5787 2299887
Year 4 3224251 4594920 14607676 0.4823 1554905
TOTAL 9480029


The Net NPV after 4 years is -532727

At 20% discount rate the NPV is negative (9480029 - 10012756 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Color.proteus Proteus to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Color.proteus Proteus has a NPV value higher than Zero then finance managers at Color.proteus Proteus can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Color.proteus Proteus, then the stock price of the Color.proteus Proteus should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Color.proteus Proteus should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Proteus Biomedical: Making Pigs Fly

References & Further Readings

Richard G. Hamermesh, Lauren Barley, Ginger L. Graham (2018), "Proteus Biomedical: Making Pigs Fly Harvard Business Review Case Study. Published by HBR Publications.


Ventus 2 VCT PLC SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


FinecoBank SWOT Analysis / TOWS Matrix

Financial , Regional Banks


Poalim Ibi SWOT Analysis / TOWS Matrix

Financial , Investment Services


YY A SWOT Analysis / TOWS Matrix

Technology , Computer Services


Master Glory SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Credible Labs SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services


Directel SWOT Analysis / TOWS Matrix

Services , Communications Services


Kingboard Laminates SWOT Analysis / TOWS Matrix

Basic Materials , Fabricated Plastic & Rubber


Critical Control Energy SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Neopost SWOT Analysis / TOWS Matrix

Technology , Office Equipment