The Resort in Pueblo Valley (A) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for The Resort in Pueblo Valley (A) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. The Resort in Pueblo Valley (A) case study is a Harvard Business School (HBR) case study written by Christine Blondel. The The Resort in Pueblo Valley (A) (referred as “Resort Family” from here on) case study provides evaluation & decision scenario in field of Innovation & Entrepreneurship. It also touches upon business topics such as - Value proposition, Succession planning.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of The Resort in Pueblo Valley (A) Case Study


The case describes the story of three generations of a business family, who owned and managed a beautiful resort. The family story includes traumatic events like: early deaths; suicide; and remarriages and the lack of communication on succession issues. Succession took place in abrupt ways, through death of owner-managers, or threat to sell by their widows. Case (A) describes the history of the family and the business until 1996, when the second generation widow confronts the children with her determination to sell the business. Case (B), to be used after case discussion, explains what happened afterwards.


Case Authors : Christine Blondel

Topic : Innovation & Entrepreneurship

Related Areas : Succession planning




Calculating Net Present Value (NPV) at 6% for The Resort in Pueblo Valley (A) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10013626) -10013626 - -
Year 1 3464924 -6548702 3464924 0.9434 3268796
Year 2 3960608 -2588094 7425532 0.89 3524927
Year 3 3938782 1350688 11364314 0.8396 3307077
Year 4 3233441 4584129 14597755 0.7921 2561188
TOTAL 14597755 12661989




The Net Present Value at 6% discount rate is 2648363

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Payback Period
3. Internal Rate of Return
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Resort Family have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Resort Family shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of The Resort in Pueblo Valley (A)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Innovation & Entrepreneurship Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Resort Family often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Resort Family needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10013626) -10013626 - -
Year 1 3464924 -6548702 3464924 0.8696 3012977
Year 2 3960608 -2588094 7425532 0.7561 2994789
Year 3 3938782 1350688 11364314 0.6575 2589813
Year 4 3233441 4584129 14597755 0.5718 1848730
TOTAL 10446310


The Net NPV after 4 years is 432684

(10446310 - 10013626 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10013626) -10013626 - -
Year 1 3464924 -6548702 3464924 0.8333 2887437
Year 2 3960608 -2588094 7425532 0.6944 2750422
Year 3 3938782 1350688 11364314 0.5787 2279388
Year 4 3233441 4584129 14597755 0.4823 1559337
TOTAL 9476584


The Net NPV after 4 years is -537042

At 20% discount rate the NPV is negative (9476584 - 10013626 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Resort Family to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Resort Family has a NPV value higher than Zero then finance managers at Resort Family can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Resort Family, then the stock price of the Resort Family should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Resort Family should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of The Resort in Pueblo Valley (A)

References & Further Readings

Christine Blondel (2018), "The Resort in Pueblo Valley (A) Harvard Business Review Case Study. Published by HBR Publications.


F5 Networks SWOT Analysis / TOWS Matrix

Technology , Computer Networks


Hangzhou Gaoxin Rubber & Plastic SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber


PLDT ADR SWOT Analysis / TOWS Matrix

Services , Communications Services


Tiansheng Pharma SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Solid State SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Shanghai Sanmao Enterprise B SWOT Analysis / TOWS Matrix

Consumer Cyclical , Textiles - Non Apparel


BT Group SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Hokuetsu Industries SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods