Carrier Corporation, Montluel, France: The Aquasnap Design Project Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Carrier Corporation, Montluel, France: The Aquasnap Design Project case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Carrier Corporation, Montluel, France: The Aquasnap Design Project case study is a Harvard Business School (HBR) case study written by Emily Jean Gibbons, Kamalini Ramdas. The Carrier Corporation, Montluel, France: The Aquasnap Design Project (referred as “Aquasnap Carrier” from here on) case study provides evaluation & decision scenario in field of Innovation & Entrepreneurship. It also touches upon business topics such as - Value proposition, Design, Product development.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Carrier Corporation, Montluel, France: The Aquasnap Design Project Case Study


This case focuses on product design as a source of competitive advantage. In the late 1990s, Carrier France faced extremely high labor and overhead costs relative to smaller Italian competitors in one segment. The only way Carrier could compete was by designing a product with low labor costs. While one design alternative would lower assembly costs and space requirements, market acceptance was unpredictable. Relative to another more conservative design alternative, a delayed launch was likely. The case contains rich qualitative and quantitative information on the costs and benefits of the two Aquasnap design concepts in consideration, and focuses on which alternative to introduce.


Case Authors : Emily Jean Gibbons, Kamalini Ramdas

Topic : Innovation & Entrepreneurship

Related Areas : Design, Product development




Calculating Net Present Value (NPV) at 6% for Carrier Corporation, Montluel, France: The Aquasnap Design Project Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10016164) -10016164 - -
Year 1 3458590 -6557574 3458590 0.9434 3262821
Year 2 3976107 -2581467 7434697 0.89 3538721
Year 3 3936888 1355421 11371585 0.8396 3305487
Year 4 3238353 4593774 14609938 0.7921 2565079
TOTAL 14609938 12672108




The Net Present Value at 6% discount rate is 2655944

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Payback Period
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Aquasnap Carrier shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Aquasnap Carrier have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Carrier Corporation, Montluel, France: The Aquasnap Design Project

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Innovation & Entrepreneurship Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Aquasnap Carrier often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Aquasnap Carrier needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10016164) -10016164 - -
Year 1 3458590 -6557574 3458590 0.8696 3007470
Year 2 3976107 -2581467 7434697 0.7561 3006508
Year 3 3936888 1355421 11371585 0.6575 2588568
Year 4 3238353 4593774 14609938 0.5718 1851539
TOTAL 10454084


The Net NPV after 4 years is 437920

(10454084 - 10016164 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10016164) -10016164 - -
Year 1 3458590 -6557574 3458590 0.8333 2882158
Year 2 3976107 -2581467 7434697 0.6944 2761185
Year 3 3936888 1355421 11371585 0.5787 2278292
Year 4 3238353 4593774 14609938 0.4823 1561706
TOTAL 9483341


The Net NPV after 4 years is -532823

At 20% discount rate the NPV is negative (9483341 - 10016164 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Aquasnap Carrier to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Aquasnap Carrier has a NPV value higher than Zero then finance managers at Aquasnap Carrier can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Aquasnap Carrier, then the stock price of the Aquasnap Carrier should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Aquasnap Carrier should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Carrier Corporation, Montluel, France: The Aquasnap Design Project

References & Further Readings

Emily Jean Gibbons, Kamalini Ramdas (2018), "Carrier Corporation, Montluel, France: The Aquasnap Design Project Harvard Business Review Case Study. Published by HBR Publications.


Taihei Machinery Works SWOT Analysis / TOWS Matrix

Capital Goods , Constr. & Agric. Machinery


Shenzhen Sinovatio A SWOT Analysis / TOWS Matrix

Technology , Communications Equipment


Carmat SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Enquest SWOT Analysis / TOWS Matrix

Energy , Oil & Gas Operations


BEML SWOT Analysis / TOWS Matrix

Capital Goods , Constr. & Agric. Machinery


SOCAM Development SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


MBL Group SWOT Analysis / TOWS Matrix

Services , Motion Pictures


Qianhe Condiment and Food SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing