Lincoln Financial Meets the Financial Crisis Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Lincoln Financial Meets the Financial Crisis case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Lincoln Financial Meets the Financial Crisis case study is a Harvard Business School (HBR) case study written by Robert C. Pozen, Peter Spring. The Lincoln Financial Meets the Financial Crisis (referred as “Lincoln Glass” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Recession.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Lincoln Financial Meets the Financial Crisis Case Study


In March of 2009, Lincoln Financial Group's CEO Dennis Glass was facing a difficult decision as to how he would replenish his company's capital, which could quickly fall to dangerously low levels as a result of the financial crisis. Though the cost of raising capital in the private sector was much higher than a government bailout, the latter also came with strings attached, including restrictions on executive compensation, limitations on dividends and potential damage to the company's brand among its stakeholders. Glass needed to weigh the pros and cons of private capital versus federal assistance, or somehow combine the two. This case reviews the impact of the financial crisis on the life insurance and annuity industry by analyzing the options available to Glass at Lincoln Financial.


Case Authors : Robert C. Pozen, Peter Spring

Topic : Leadership & Managing People

Related Areas : Recession




Calculating Net Present Value (NPV) at 6% for Lincoln Financial Meets the Financial Crisis Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10013504) -10013504 - -
Year 1 3448292 -6565212 3448292 0.9434 3253106
Year 2 3961486 -2603726 7409778 0.89 3525708
Year 3 3963676 1359950 11373454 0.8396 3327979
Year 4 3228611 4588561 14602065 0.7921 2557362
TOTAL 14602065 12664155




The Net Present Value at 6% discount rate is 2650651

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Internal Rate of Return
3. Payback Period
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Lincoln Glass shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Lincoln Glass have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Lincoln Financial Meets the Financial Crisis

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Lincoln Glass often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Lincoln Glass needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10013504) -10013504 - -
Year 1 3448292 -6565212 3448292 0.8696 2998515
Year 2 3961486 -2603726 7409778 0.7561 2995453
Year 3 3963676 1359950 11373454 0.6575 2606181
Year 4 3228611 4588561 14602065 0.5718 1845969
TOTAL 10446117


The Net NPV after 4 years is 432613

(10446117 - 10013504 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10013504) -10013504 - -
Year 1 3448292 -6565212 3448292 0.8333 2873577
Year 2 3961486 -2603726 7409778 0.6944 2751032
Year 3 3963676 1359950 11373454 0.5787 2293794
Year 4 3228611 4588561 14602065 0.4823 1557008
TOTAL 9475410


The Net NPV after 4 years is -538094

At 20% discount rate the NPV is negative (9475410 - 10013504 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Lincoln Glass to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Lincoln Glass has a NPV value higher than Zero then finance managers at Lincoln Glass can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Lincoln Glass, then the stock price of the Lincoln Glass should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Lincoln Glass should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Lincoln Financial Meets the Financial Crisis

References & Further Readings

Robert C. Pozen, Peter Spring (2018), "Lincoln Financial Meets the Financial Crisis Harvard Business Review Case Study. Published by HBR Publications.


NFI Group SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Manufacturers


MaxCyte SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Sanmina SWOT Analysis / TOWS Matrix

Technology , Semiconductors


Showa Paxxs SWOT Analysis / TOWS Matrix

Basic Materials , Containers & Packaging


Velesto Energy SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


Zhejiang Guangsha SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Hon Corp SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services