Children's Hospital Boston (A) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Children's Hospital Boston (A) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Children's Hospital Boston (A) case study is a Harvard Business School (HBR) case study written by Scott A. Snook, Jeffrey C. Connor. The Children's Hospital Boston (A) (referred as “Children's Death” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Crisis management, Influence, Leadership, Leading teams, Risk management.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Children's Hospital Boston (A) Case Study


Five year old Matty died at Children's Hospital Boston as a result of elective neurosurgery to "cure" his epilepsy. The organizational system, not the surgery, had failed. During post-operative recovery, he experienced a prolonged seizure that resulted in his death. Confused leadership, organizational differentiation, structurally induced silence, and organizational mis-alignment contributed to the death. How could this happen in such a world class medical facility?


Case Authors : Scott A. Snook, Jeffrey C. Connor

Topic : Leadership & Managing People

Related Areas : Crisis management, Influence, Leadership, Leading teams, Risk management




Calculating Net Present Value (NPV) at 6% for Children's Hospital Boston (A) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10002789) -10002789 - -
Year 1 3447910 -6554879 3447910 0.9434 3252745
Year 2 3959254 -2595625 7407164 0.89 3523722
Year 3 3957412 1361787 11364576 0.8396 3322719
Year 4 3240855 4602642 14605431 0.7921 2567061
TOTAL 14605431 12666247




The Net Present Value at 6% discount rate is 2663458

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Internal Rate of Return
3. Net Present Value
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Children's Death have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Children's Death shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Children's Hospital Boston (A)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Children's Death often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Children's Death needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10002789) -10002789 - -
Year 1 3447910 -6554879 3447910 0.8696 2998183
Year 2 3959254 -2595625 7407164 0.7561 2993765
Year 3 3957412 1361787 11364576 0.6575 2602063
Year 4 3240855 4602642 14605431 0.5718 1852969
TOTAL 10446979


The Net NPV after 4 years is 444190

(10446979 - 10002789 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10002789) -10002789 - -
Year 1 3447910 -6554879 3447910 0.8333 2873258
Year 2 3959254 -2595625 7407164 0.6944 2749482
Year 3 3957412 1361787 11364576 0.5787 2290169
Year 4 3240855 4602642 14605431 0.4823 1562912
TOTAL 9475822


The Net NPV after 4 years is -526967

At 20% discount rate the NPV is negative (9475822 - 10002789 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Children's Death to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Children's Death has a NPV value higher than Zero then finance managers at Children's Death can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Children's Death, then the stock price of the Children's Death should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Children's Death should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Children's Hospital Boston (A)

References & Further Readings

Scott A. Snook, Jeffrey C. Connor (2018), "Children's Hospital Boston (A) Harvard Business Review Case Study. Published by HBR Publications.


Delticom AG SWOT Analysis / TOWS Matrix

Services , Retail (Catalog & Mail Order)


Metropole TV SWOT Analysis / TOWS Matrix

Services , Broadcasting & Cable TV


Zigexn SWOT Analysis / TOWS Matrix

Technology , Computer Services


Japan Medical Dynamic SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Ichimasa Kamaboko SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


C&N Holdings SWOT Analysis / TOWS Matrix

Services , Business Services


Rimo International Lestari SWOT Analysis / TOWS Matrix

Services , Retail (Department & Discount)


Takasago Thermal Eng SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Carbo Ceramics SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment