Thompson Asset Management, Portuguese Version Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Thompson Asset Management, Portuguese Version case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Thompson Asset Management, Portuguese Version case study is a Harvard Business School (HBR) case study written by William E. Fruhan, John Banko. The Thompson Asset Management, Portuguese Version (referred as “Thompson Asset” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Financial management, Growth strategy, Risk management.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Thompson Asset Management, Portuguese Version Case Study


Thompson Asset Management (TAM) is a small investment advisory and asset management firm in Jacksonville, Florida, with about $100 million in assets under management in two different funds. Since starting the firm in 2009, the CEO and founder Allison Thompson has had a proven track record of beating benchmarks and managing the portfolio's downside risk. The firm's typical clients were high-net-worth individuals, and in 2014, Thompson is looking to expand her business by taking on institutional clients as well. She recently met with the investment officer of her alma mater and is considering taking on the university's endowment fund as a client. For her bid to manage the entire endowment of $20 million, Thompson must create a presentation that outlines her investment strategy. The case is ideal for an MBA-level or undergraduate finance course that covers asset management and/or portfolio theory.


Case Authors : William E. Fruhan, John Banko

Topic : Finance & Accounting

Related Areas : Financial management, Growth strategy, Risk management




Calculating Net Present Value (NPV) at 6% for Thompson Asset Management, Portuguese Version Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10007277) -10007277 - -
Year 1 3471619 -6535658 3471619 0.9434 3275112
Year 2 3953381 -2582277 7425000 0.89 3518495
Year 3 3939577 1357300 11364577 0.8396 3307745
Year 4 3226952 4584252 14591529 0.7921 2556048
TOTAL 14591529 12657400




The Net Present Value at 6% discount rate is 2650123

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Net Present Value
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Thompson Asset have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Thompson Asset shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Thompson Asset Management, Portuguese Version

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Thompson Asset often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Thompson Asset needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10007277) -10007277 - -
Year 1 3471619 -6535658 3471619 0.8696 3018799
Year 2 3953381 -2582277 7425000 0.7561 2989324
Year 3 3939577 1357300 11364577 0.6575 2590336
Year 4 3226952 4584252 14591529 0.5718 1845020
TOTAL 10443479


The Net NPV after 4 years is 436202

(10443479 - 10007277 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10007277) -10007277 - -
Year 1 3471619 -6535658 3471619 0.8333 2893016
Year 2 3953381 -2582277 7425000 0.6944 2745403
Year 3 3939577 1357300 11364577 0.5787 2279848
Year 4 3226952 4584252 14591529 0.4823 1556208
TOTAL 9474475


The Net NPV after 4 years is -532802

At 20% discount rate the NPV is negative (9474475 - 10007277 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Thompson Asset to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Thompson Asset has a NPV value higher than Zero then finance managers at Thompson Asset can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Thompson Asset, then the stock price of the Thompson Asset should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Thompson Asset should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Thompson Asset Management, Portuguese Version

References & Further Readings

William E. Fruhan, John Banko (2018), "Thompson Asset Management, Portuguese Version Harvard Business Review Case Study. Published by HBR Publications.


Stella-Jones Inc. SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Incentiapay SWOT Analysis / TOWS Matrix

Technology , Software & Programming


OpenSys M SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Tae Won Mulsan SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Parts


Johnson Electric SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Parts


Zhejiang Henglin Chair A SWOT Analysis / TOWS Matrix

Consumer Cyclical , Furniture & Fixtures


Ross Group PLC SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Esprinet SWOT Analysis / TOWS Matrix

Technology , Computer Hardware