Rick Drumm (A) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Rick Drumm (A) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Rick Drumm (A) case study is a Harvard Business School (HBR) case study written by J. B.M. Kassarjian. The Rick Drumm (A) (referred as “Rick D'addario” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Leadership, Organizational culture, Professional transitions.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Rick Drumm (A) Case Study


Rick Drumm (his real name), once a teen-age drumming contest winner, is facing the most promising, but also the most challenging, career transition in his career as a manager and a leader. While a second-year MBA student in a fast-track program, and working as President of Vic Firth Inc, a $20 million-sales drumstick manufacturer, he is being recruited to become president of J. D'Addario & Co., the largest manufacturer of musical accessories in the US. Having survived a series of interviews - by the headhunter, various Board members, and the Chairman of D'Addario - he is informed that he has to be interviewed by Jack Welch, the legendary CEO of General Electric, as the final step in his selection process. Rick has to decide how to prepare for this interview, how to approach this final test of his qualifications to assume the leadership of a much larger and more complex organization. The (A) case describes his concerns and questions about the up-coming interview. It also paints the scenario of Ricks personal history, and the sometimes colorful career transitions he has gone through up to this latest opportunity. Critical themes are highlighted, tracing the central threads of his development as a manager. The (A) case ends with Rick ringing the bell at Welch's Boston residence on a cold afternoon in December.


Case Authors : J. B.M. Kassarjian

Topic : Leadership & Managing People

Related Areas : Leadership, Organizational culture, Professional transitions




Calculating Net Present Value (NPV) at 6% for Rick Drumm (A) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10027147) -10027147 - -
Year 1 3443206 -6583941 3443206 0.9434 3248308
Year 2 3962585 -2621356 7405791 0.89 3526687
Year 3 3946460 1325104 11352251 0.8396 3313524
Year 4 3248259 4573363 14600510 0.7921 2572925
TOTAL 14600510 12661443




The Net Present Value at 6% discount rate is 2634296

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Net Present Value
3. Internal Rate of Return
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Rick D'addario have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Rick D'addario shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Rick Drumm (A)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Rick D'addario often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Rick D'addario needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10027147) -10027147 - -
Year 1 3443206 -6583941 3443206 0.8696 2994092
Year 2 3962585 -2621356 7405791 0.7561 2996284
Year 3 3946460 1325104 11352251 0.6575 2594862
Year 4 3248259 4573363 14600510 0.5718 1857203
TOTAL 10442440


The Net NPV after 4 years is 415293

(10442440 - 10027147 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10027147) -10027147 - -
Year 1 3443206 -6583941 3443206 0.8333 2869338
Year 2 3962585 -2621356 7405791 0.6944 2751795
Year 3 3946460 1325104 11352251 0.5787 2283831
Year 4 3248259 4573363 14600510 0.4823 1566483
TOTAL 9471447


The Net NPV after 4 years is -555700

At 20% discount rate the NPV is negative (9471447 - 10027147 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Rick D'addario to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Rick D'addario has a NPV value higher than Zero then finance managers at Rick D'addario can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Rick D'addario, then the stock price of the Rick D'addario should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Rick D'addario should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Rick Drumm (A)

References & Further Readings

J. B.M. Kassarjian (2018), "Rick Drumm (A) Harvard Business Review Case Study. Published by HBR Publications.


Space Solution SWOT Analysis / TOWS Matrix

Technology , Computer Services


Mitsubishi Electric SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Broadex Tech SWOT Analysis / TOWS Matrix

Technology , Communications Equipment


Select Harvests SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Electro-Sensors SWOT Analysis / TOWS Matrix

Technology , Scientific & Technical Instr.


Menang Corp SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Ecovacs Robotics SWOT Analysis / TOWS Matrix

Consumer Cyclical , Appliance & Tool


AFC Energy SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls