Sherif Mityas at A.T. Kearney: Negotiating a Client Service Predicament (A) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Sherif Mityas at A.T. Kearney: Negotiating a Client Service Predicament (A) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Sherif Mityas at A.T. Kearney: Negotiating a Client Service Predicament (A) case study is a Harvard Business School (HBR) case study written by Ashish Nanda, Kelley Morrell. The Sherif Mityas at A.T. Kearney: Negotiating a Client Service Predicament (A) (referred as “Mityas Midproject” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Cross-cultural management, Customers, Ethics, Strategy.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Sherif Mityas at A.T. Kearney: Negotiating a Client Service Predicament (A) Case Study


Sherif Mityas, recently promoted as project manager at A.T. Kearney, faced a client service challenge in his very first project experience. Mityas had been working closely for six weeks with the management team of the U.S. subsidiary of a Japan-headquartered consumer products company to identify ways to turn around the U.S. operations. Following the midproject status meeting, executives from the Japanese parent company made an unexpected request that placed Mityas in a quandary. Mityas related the situation: "At the conclusion of the midproject meeting, I felt confident that we had made solid recommendations about turning around the U.S. operations, but the Japanese parent company executives made a difficult request. They wanted us to evaluate the ability of the U.S. management team to carry out the turnaround. U.S. management had been instrumental in our being able to understand and analyze the situation comprehensively, and we would need their cooperation for our future work to be meaningful. If they came to know that we were simultaneously evaluating them, we could lose their trust--but, then, the Japanese executives represented the client. I didn't know how to proceed."


Case Authors : Ashish Nanda, Kelley Morrell

Topic : Leadership & Managing People

Related Areas : Cross-cultural management, Customers, Ethics, Strategy




Calculating Net Present Value (NPV) at 6% for Sherif Mityas at A.T. Kearney: Negotiating a Client Service Predicament (A) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10003469) -10003469 - -
Year 1 3467274 -6536195 3467274 0.9434 3271013
Year 2 3955048 -2581147 7422322 0.89 3519979
Year 3 3951260 1370113 11373582 0.8396 3317554
Year 4 3247428 4617541 14621010 0.7921 2572267
TOTAL 14621010 12680813




The Net Present Value at 6% discount rate is 2677344

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Payback Period
3. Net Present Value
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Mityas Midproject shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Mityas Midproject have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Sherif Mityas at A.T. Kearney: Negotiating a Client Service Predicament (A)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Mityas Midproject often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Mityas Midproject needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10003469) -10003469 - -
Year 1 3467274 -6536195 3467274 0.8696 3015021
Year 2 3955048 -2581147 7422322 0.7561 2990584
Year 3 3951260 1370113 11373582 0.6575 2598018
Year 4 3247428 4617541 14621010 0.5718 1856727
TOTAL 10460350


The Net NPV after 4 years is 456881

(10460350 - 10003469 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10003469) -10003469 - -
Year 1 3467274 -6536195 3467274 0.8333 2889395
Year 2 3955048 -2581147 7422322 0.6944 2746561
Year 3 3951260 1370113 11373582 0.5787 2286609
Year 4 3247428 4617541 14621010 0.4823 1566082
TOTAL 9488647


The Net NPV after 4 years is -514822

At 20% discount rate the NPV is negative (9488647 - 10003469 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Mityas Midproject to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Mityas Midproject has a NPV value higher than Zero then finance managers at Mityas Midproject can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Mityas Midproject, then the stock price of the Mityas Midproject should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Mityas Midproject should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Sherif Mityas at A.T. Kearney: Negotiating a Client Service Predicament (A)

References & Further Readings

Ashish Nanda, Kelley Morrell (2018), "Sherif Mityas at A.T. Kearney: Negotiating a Client Service Predicament (A) Harvard Business Review Case Study. Published by HBR Publications.


Global Eagle SWOT Analysis / TOWS Matrix

Services , Communications Services


Dynam Japan SWOT Analysis / TOWS Matrix

Services , Casinos & Gaming


Worth Peripherals SWOT Analysis / TOWS Matrix

Basic Materials , Containers & Packaging


System Integrator SWOT Analysis / TOWS Matrix

Technology , Software & Programming


China Unicom Hong Kong SWOT Analysis / TOWS Matrix

Services , Communications Services


UB Care SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Makism 3D Corp SWOT Analysis / TOWS Matrix

Technology , Computer Peripherals


Maruman & SWOT Analysis / TOWS Matrix

Consumer Cyclical , Recreational Products


Nisshinbo Holdings Inc. SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls