Implementing Sustainable IT Strategy: The Case of Intel Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Implementing Sustainable IT Strategy: The Case of Intel case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Implementing Sustainable IT Strategy: The Case of Intel case study is a Harvard Business School (HBR) case study written by Edward Curry, Brian Donnellan. The Implementing Sustainable IT Strategy: The Case of Intel (referred as “Sustainable Intel” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Sustainability.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Implementing Sustainable IT Strategy: The Case of Intel Case Study


Sustainable IT (Information Technology) involves the responsible management of resources (both IT and non-IT) encompassing environmental, economic, and social dimensions. Sustainable IT has the potential to be a significant contributor to an organization's sustainability strategy. In this teaching case, we examine what Intel IT has done to transform its operations with Sustainable IT, resulting in the avoidance of significant CO2 emissions and cost savings. This teaching case challenges the reader to analyze the Sustainable IT capability at Intel. The case includes insights into strategic and operational challenges of planning and managing Sustainable IT.


Case Authors : Edward Curry, Brian Donnellan

Topic : Leadership & Managing People

Related Areas : Sustainability




Calculating Net Present Value (NPV) at 6% for Implementing Sustainable IT Strategy: The Case of Intel Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10027176) -10027176 - -
Year 1 3454896 -6572280 3454896 0.9434 3259336
Year 2 3978925 -2593355 7433821 0.89 3541229
Year 3 3941340 1347985 11375161 0.8396 3309225
Year 4 3241925 4589910 14617086 0.7921 2567908
TOTAL 14617086 12677698




The Net Present Value at 6% discount rate is 2650522

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Net Present Value
3. Internal Rate of Return
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Sustainable Intel shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Sustainable Intel have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Implementing Sustainable IT Strategy: The Case of Intel

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Sustainable Intel often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Sustainable Intel needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10027176) -10027176 - -
Year 1 3454896 -6572280 3454896 0.8696 3004257
Year 2 3978925 -2593355 7433821 0.7561 3008639
Year 3 3941340 1347985 11375161 0.6575 2591495
Year 4 3241925 4589910 14617086 0.5718 1853581
TOTAL 10457973


The Net NPV after 4 years is 430797

(10457973 - 10027176 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10027176) -10027176 - -
Year 1 3454896 -6572280 3454896 0.8333 2879080
Year 2 3978925 -2593355 7433821 0.6944 2763142
Year 3 3941340 1347985 11375161 0.5787 2280868
Year 4 3241925 4589910 14617086 0.4823 1563428
TOTAL 9486519


The Net NPV after 4 years is -540657

At 20% discount rate the NPV is negative (9486519 - 10027176 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Sustainable Intel to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Sustainable Intel has a NPV value higher than Zero then finance managers at Sustainable Intel can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Sustainable Intel, then the stock price of the Sustainable Intel should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Sustainable Intel should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Implementing Sustainable IT Strategy: The Case of Intel

References & Further Readings

Edward Curry, Brian Donnellan (2018), "Implementing Sustainable IT Strategy: The Case of Intel Harvard Business Review Case Study. Published by HBR Publications.


Impack Pratama Industri SWOT Analysis / TOWS Matrix

Basic Materials , Fabricated Plastic & Rubber


Huajun SWOT Analysis / TOWS Matrix

Technology , Semiconductors


EW Scripps A SWOT Analysis / TOWS Matrix

Services , Broadcasting & Cable TV


Alumina SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining


Myer Holdings SWOT Analysis / TOWS Matrix

Services , Retail (Department & Discount)


Shuanghui Dev A SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Newmark Group SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Sariguna Primatirta SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Zhejiang Expressway SWOT Analysis / TOWS Matrix

Transportation , Misc. Transportation