Northwest Airlines Confronts Change Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Northwest Airlines Confronts Change case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Northwest Airlines Confronts Change case study is a Harvard Business School (HBR) case study written by Todd D. Jick, Susan Rosegrant. The Northwest Airlines Confronts Change (referred as “Northwest Rothmeier” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Leadership.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Northwest Airlines Confronts Change Case Study


Describes the leadership role of Northwest Airlines' chairman and his key organizational development "lieutenant" during five years of major change and pressure--1985-89. During this time the airline was confronted with major customer service problems, the merger with Republic, and the crash of one of its planes. Highlights the roles, responsibilities, and tactics of Steve Rothmeier and Ken Myers during this turbulent period. Can be used to evaluate leadership in times of difficult pressures, the different styles of change that each embodies and advocates, and the results of their actions.


Case Authors : Todd D. Jick, Susan Rosegrant

Topic : Leadership & Managing People

Related Areas : Leadership




Calculating Net Present Value (NPV) at 6% for Northwest Airlines Confronts Change Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10019051) -10019051 - -
Year 1 3448050 -6571001 3448050 0.9434 3252877
Year 2 3955235 -2615766 7403285 0.89 3520145
Year 3 3949426 1333660 11352711 0.8396 3316014
Year 4 3228884 4562544 14581595 0.7921 2557579
TOTAL 14581595 12646615




The Net Present Value at 6% discount rate is 2627564

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Internal Rate of Return
3. Net Present Value
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Northwest Rothmeier have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Northwest Rothmeier shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Northwest Airlines Confronts Change

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Northwest Rothmeier often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Northwest Rothmeier needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10019051) -10019051 - -
Year 1 3448050 -6571001 3448050 0.8696 2998304
Year 2 3955235 -2615766 7403285 0.7561 2990726
Year 3 3949426 1333660 11352711 0.6575 2596812
Year 4 3228884 4562544 14581595 0.5718 1846125
TOTAL 10431967


The Net NPV after 4 years is 412916

(10431967 - 10019051 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10019051) -10019051 - -
Year 1 3448050 -6571001 3448050 0.8333 2873375
Year 2 3955235 -2615766 7403285 0.6944 2746691
Year 3 3949426 1333660 11352711 0.5787 2285547
Year 4 3228884 4562544 14581595 0.4823 1557139
TOTAL 9462753


The Net NPV after 4 years is -556298

At 20% discount rate the NPV is negative (9462753 - 10019051 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Northwest Rothmeier to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Northwest Rothmeier has a NPV value higher than Zero then finance managers at Northwest Rothmeier can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Northwest Rothmeier, then the stock price of the Northwest Rothmeier should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Northwest Rothmeier should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Northwest Airlines Confronts Change

References & Further Readings

Todd D. Jick, Susan Rosegrant (2018), "Northwest Airlines Confronts Change Harvard Business Review Case Study. Published by HBR Publications.


Torishima Pump Mfg SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


Jiangsu Yueda Invest SWOT Analysis / TOWS Matrix

Consumer Cyclical , Textiles - Non Apparel


Primus Guaranty SWOT Analysis / TOWS Matrix

Financial , Investment Services


Jiangxi Sanxin Medtec Co Ltd SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Schneider Electric SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Pantronics Holdings Ltd SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Daeho Al SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining


Real Estate Credit SWOT Analysis / TOWS Matrix

Financial , Investment Services